Follow Us! Like Our Page!

B2Gold Reports Q4 and Full Year 2024 Results; Achieved 2024 Total Gold Production and Consolidated Cost Guidance; Goose Project Remains On Track for First Gold in Q2 2025 and Total Capital Estimate Remains at C$1,540 Million; Q1 2025 Dividend of US$0.02 per Share Declared

Press Release

February 19, 2025

VANCOUVER, British Columbia, Feb. 19, 2025 B2Gold Corp. (TSX: BTO, NYSE AMERICAN: BTG, NSX: B2G) (“B2Gold” or the “Company”) announces its operational and financial results for the fourth quarter and full year 2024. The Company previously released its gold production and gold revenue results for the fourth quarter and full year 2024. All dollar figures are in United States dollars unless otherwise indicated.

2024 Fourth Quarter and Full Year Highlights

  • Total gold production of 186,001 ounces in Q4 2024: Total gold production in the fourth quarter of 2024 was 186,001 ounces. Masbate and Otjikoto both continued to outperform expectations in the fourth quarter of 2024, which partially offset lower than expected production levels at Fekola during the quarter due to the continued delays in accessing higher-grade ore from Fekola Phase 7, a result of lower realized mine production from the Fekola Phase 7 and Cardinal pits during the period. Mining and processing of these higher-grade tonnes is now expected in 2025 as equipment availability had returned to full capacity and mining rates were at expected levels at the end of 2024. All three operations are meeting or exceeding gold production expectations to start 2025.
  • Total consolidated cash operating costs of $968 per gold ounce produced in Q4 2024: Total consolidated cash operating costs (see “Non-IFRS Measures”) were $968 per gold ounce produced during the fourth quarter of 2024, higher than expected as a result of lower than anticipated production in the quarter.
  • Total consolidated all-in sustaining costs of $1,668 per gold ounce sold in Q4 2024: Total consolidated all-in sustaining costs (see “Non-IFRS Measures”) were $1,668 per gold ounce sold during the fourth quarter of 2024, higher than expected as a result of lower than anticipated gold ounces sold resulting from lower than anticipated production, higher than expected royalties resulting from a higher than anticipated gold price, and new royalties implemented in 2024 for Fekola.
  • Total annual consolidated gold production of 804,778 ounces: Total consolidated gold production for 2024 was 804,778 ounces (including 19,644 attributable ounces from Calibre Mining Corp. (“Calibre”)), at the low end of the Company’s 2024 guidance range.
  • Total consolidated cash operating costs and all-in sustaining costs for 2024 within their guidance ranges: Total consolidated cash operating costs for 2024 were $889 per gold ounce produced, at the upper end of the annual guidance range of between $835 and $895 per gold ounce. Total consolidated all-in sustaining costs for 2024 were $1,465 per gold ounce sold, within the annual guidance range of between $1,420 and $1,480 per gold ounce.
  • Attributable net loss of $0.01 per share in Q4 2024; Adjusted attributable net income of $0.01 per share in Q4 2024: Net loss attributable to the shareholders of the Company of $12 million ($0.01 per share); adjusted net income (see “Non-IFRS Measures”) attributable to the shareholders of the Company of $17 million ($0.01 per share). Net loss attributable to the shareholders of the Company for the year ended December 31, 2024 was $630 million ($0.48 per share), predominantly due to non-cash impairment charges on the Goose Project and the Fekola Complex, and adjusted net income (see “Non-IFRS Measures”) attributable to the shareholders of the Company was $207 million ($0.16 per share).
  • Operating cash flow before working capital adjustments of $145 million in Q4 2024: Cash flow provided by operating activities before working capital adjustments was $145 million in the fourth quarter of 2024. Cash flow provided by operating activities before working capital adjustments and proceeds from the gold prepay arrangement for the year ended December 31, 2024 was $660 million.
  • Strong financial position and liquidity: At December 31, 2024, the Company had cash and cash equivalents of $337 million and working capital (defined as current assets less current liabilities) of $321 million.
  • Goose Project construction and development continues to progress on track for first gold pour in the second quarter of 2025: All planned construction activities in 2024 were completed and project construction and development continue to progress on track for first gold pour at the Goose Project in the second quarter of 2025 followed by ramp up to commercial production in the third quarter of 2025.
  • 2025 Winter Ice Road (“WIR”) Campaign Commenced at the Goose Project: Following the successful completion of the 2024 sea lift, construction of the 163 kilometer (“km”) WIR began in December 2024 and was completed in February 2025. As of February 18, 2025, the WIR is operational with the transportation of all materials from the Marine Laydown Area (“MLA”) to the Goose Project site expected to be completed by May 15, 2025.
  • Total Goose Project construction and mine development cash expenditure estimate before first production remains at C$1,540 million: Based on the construction and mine development cash expenditures incurred to date, combined with the estimated expenditures to be incurred through to the first gold pour in the second quarter of 2025, the Company reiterates the total Goose Project construction and mine development cash expenditure estimate of C$1,540 million.
  • B2Gold’s initial Goose Project life of mine plan to be released at the end of the first quarter of 2025 based on updated Mineral Reserves: The Company continues to estimate that gold production in calendar year 2025 will be between 120,000 and 150,000 ounces and that average annual gold production for the six year period from 2026 to 2031 inclusive will be approximately 310,000 ounces per year, with the latest published Mineral Reserves supporting a long mine life beyond 2031.
  • Feasibility Study on the Gramalote Project in Colombia underway and targeted for completion in mid-2025: The positive Preliminary Economic Assessment (“PEA”) results on the Company’s 100% owned Gramalote Project, completed in the second quarter of 2024, outlined a significant production profile with average annual gold production of 234,000 ounces per year for the first five years of production, and strong project economics over a 12.5 year project life. As a result, B2Gold commenced work on a feasibility study with the goal of completion in mid-2025. Feasibility work including geotechnical investigation, processing design and site infrastructure design is underway and the study remains on schedule.
  • Subsequent to year-end 2024, positive PEA results for the Antelope deposit at the Otjikoto Mine in Namibia were announced: On February 4, 2025, the Company announced positive PEA results for the Antelope deposit, located approximately 4 km southwest of the existing Otjikoto open pit. Based on the positive results from the PEA, B2Gold believes that the Antelope deposit has the potential to become a small-scale, low-cost, underground gold mine that can supplement the low-grade stockpile production during the period of 2028 to 2032 and result in a meaningful production profile for Otjikoto into the next decade. The PEA for the Antelope deposit indicates an initial mine life of 5 years and total production of 327,000 ounces averaging approximately 65,000 ounces per year over the life of mine. In combination with the processing of existing low grade stockpiles, production from the Antelope deposit has the potential to increase Otjikoto Mine production to approximately 110,000 ounces per year for 2029 through 2032.
  • Subsequent to year-end 2024, issued convertible senior unsecured notes: On January 28, 2025, the Company issued 2.75% convertible senior unsecured notes due 2030 (the “Notes”) with an aggregate principal amount of $460 million. The initial conversion rate for the Notes is 315.2088 common shares of the Company (the “Shares”) per $1,000 principal amount of Notes, equivalent to an initial conversion price of approximately $3.17 per Share. The initial conversion rate represents a premium of approximately 35% relative to the closing sale price of the Shares on January 23, 2025 and is subject to adjustment in certain events. The Company intends to use the net proceeds to fund working capital requirements and for general corporate purposes.
  • Q1 2025 dividend of $0.02 per share declared: On February 19, 2025, B2Gold’s Board of Directors declared a cash dividend for the first quarter of 2025 of $0.02 per common share (or an expected $0.08 per share on an annualized basis), payable on March 20, 2025, to shareholders of record as of March 7, 2025.

Fourth Quarter and Full Year 2024 Results

Read More:

IBF4

Loading

NationTalk Partners & Sponsors Learn More