TORONTO, ON – Denison Mines Corp. (“Denison” or the “Company”) (TSX: DML) (NYSE American: DNN) today filed its Audited Consolidated Financial Statements and Management’s Discussion & Analysis (“MD&A”) for the year ended December 31, 2020. Both documents can be found on the Company’s website at www.denisonmines.com or on SEDAR (at www.sedar.com) and EDGAR (at www.sec.gov/edgar.shtml). The highlights provided below are derived from these documents and should be read in conjunction with them. All amounts in this release are in Canadian dollars unless otherwise stated. View PDF version
David Cates, President and CEO of Denison commented, “Confronted with the varied challenges of the global COVID-19 pandemic, Denison’s resilient teams excelled in 2020 and early 2021 – accomplishing a significant de-risking of our flagship Wheeler River project and the Company’s balance sheet.
At Wheeler River, our technical team achieved a key milestone, receiving an independent confirmation of ‘Proof of Concept’ for the application of the In-Situ Recovery (‘ISR’) mining method at the high-grade Phoenix deposit. We also completed an important trade-off study leading to the adoption of a freeze ‘wall’ design for containment of the ISR operation at Phoenix – a decision that is expected to be favourable from an environmental standpoint, reduce technical complexity and operational risks, allow for a phased mining approach with lower up-front capital costs, and strengthen project sustainability. With the Environmental Assessment process fully resumed and a $21.8 million budget (Denison’s share $19.4 million) approved and funded for evaluation and environmental assessment work at Wheeler River in 2021, the entire team is now focused on advancing Phoenix through the regulatory and community consultation process to support a future Feasibility Study (“FS”), with the objective of pairing Phoenix, the world’s highest grade undeveloped uranium deposit, with ISR mining, the world’s lowest cost uranium mining method.
In 2020, the technical team also delivered positive results from the Waterbury Lake Preliminary Economic Assessment (‘PEA’), which considered the potential future development of the Tthe Heldeth Túé (‘THT’) uranium deposit as Denison’s second ISR amendable project in the Athabasca Basin region. The results were highlighted by low initial capital costs and globally competitive operating costs. Adding to Wheeler River’s Phoenix and Gryphon deposits, THT represents Denison’s third development asset with fully loaded costs (including initial capital costs, sustaining capital costs, and operating costs) estimated at under US$25 per pound U3O8.
On the Corporate side, the Company’s financial situation has also been significantly de-risked, having completed a round of critical capital raising over the last 12 months that has positioned the company with approximately $85 million in cash and investments, while remaining debt-free. Taken together, Denison is uniquely positioned as a well-capitalized uranium developer, with multiple low-cost assets, at a time when the uranium market is showing signs of incremental improvement underpinned by growing calls for nuclear energy to re-emerge as a leading technology important to a sustainable global energy transition.”
HIGHLIGHTS
About Wheeler River
Wheeler River is the largest undeveloped uranium project in the infrastructure rich eastern portion of the Athabasca Basin region, in northern Saskatchewan and is a joint venture between Denison (90% and operator) and JCU (Canada) Exploration Company Limited (10%). The project is host to the high-grade Phoenix and Gryphon uranium deposits, discovered by Denison in 2008 and 2014, respectively, estimated to have combined Indicated Mineral Resources of 132.1 million pounds U3O8 (1,809,000 tonnes at an average grade of 3.3% U3O8), plus combined Inferred Mineral Resources of 3.0 million pounds U3O8 (82,000 tonnes at an average grade of 1.7% U3O8).
The PFS was completed in late 2018, considering the potential economic merit of developing the Phoenix deposit as an ISR operation and the Gryphon deposit as a conventional underground mining operation. Taken together, the project is estimated to have mine production of 109.4 million pounds U3O8 over a 14-year mine life, with a base case pre-tax net present value (‘NPV’) of $1.31 billion (8% discount rate), Internal Rate of Return (‘IRR’) of 38.7%, and initial pre-production capital expenditures of $322.5 million. The Phoenix ISR operation is estimated to have a stand-alone base case pre-tax NPV of $930.4 million (8% discount rate), IRR of 43.3%, initial pre-production capital expenditures of $322.5 million, and industry leading average operating costs of US$3.33/lb U3O8. The PFS was prepared on a project (100% ownership) and pre-tax basis, as each of the partners to the Wheeler River Joint Venture are subject to different tax and other obligations.
Further details regarding the PFS, including additional scientific and technical information, as well as after-tax results attributable to Denison’s ownership interest, are described in greater detail in the NI 43-101 Technical Report titled “Pre-feasibility Study for the Wheeler River Uranium Project, Saskatchewan, Canada” dated October 30, 2018 with an effective date of September 24, 2018. A copy of this report is available on Denison’s website and under its profile on SEDAR at www.sedar.com and on EDGAR at www.sec.gov/edgar.shtml.
Given the social, financial and market disruptions related to COVID-19, and certain fiscally prudent measures, Denison temporarily suspended certain activities at Wheeler River starting in April 2020, including the formal parts of the EA program, which is on the critical path to achieving the project development schedule outlined in the PFS Technical Report. While the formal EA process has resumed in early 2021, the Company is not currently able to estimate the impact to the project development schedule, outlined in the PFS Technical Report, and users are cautioned that certain of the estimates provided therein, particularly regarding the start of pre-production activities in 2021 and first production in 2024 should not be relied upon.
About Denison
Denison Mines Corp. was formed under the laws of Ontario and is a reporting issuer in all Canadian provinces. Denison’s common shares are listed on the Toronto Stock Exchange (the ‘TSX’) under the symbol ‘DML’ and on the NYSE American exchange under the symbol ‘DNN’.
Denison is a uranium exploration and development company with interests focused in the Athabasca Basin region of northern Saskatchewan, Canada. In addition to the Company’s flagship project, Wheeler River, Denison’s interests in Saskatchewan include a 22.5% ownership interest in the McClean Lake Joint Venture (‘MLJV’), which includes several uranium deposits and the McClean Lake uranium mill, which is currently processing ore from the Cigar Lake mine under a toll milling agreement, plus a 25.17% interest in the Midwest deposits and a 66.90% interest in the THT and Huskie deposits on the Waterbury Lake property. The Midwest, THT and Huskie deposits are located within 20 kilometres of the McClean Lake mill. In addition, Denison has an extensive portfolio of exploration projects in the Athabasca Basin region.
Denison is engaged in mine decommissioning and environmental services through its Closed Mines group (formerly Denison Environmental Services), which manages Denison’s Elliot Lake reclamation projects and provides post-closure mine and maintenance services to a variety of industry and government clients.
Denison is also the manager of Uranium Participation Corporation (‘UPC’), a publicly traded company listed on the TSX under the symbol ‘U’, which invests in uranium oxide in concentrates (‘U3O8‘) and uranium hexafluoride (‘UF6‘).
Technical Disclosure and Qualified Person
The technical information contained in this press release has been reviewed and approved by David Bronkhorst, P.Eng, Denison’s Vice President, Operations and/or Andrew Yackulic, P. Geo, Denison’s Director, Exploration, each of whom is a Qualified Person in accordance with the requirements of NI 43-101.