Press Release
October 23, 2023 – Vancouver, Canada – First Mining Gold Corp. (“First Mining” or the “Company”) (TSX: FF) (OTCQX: FFMGF) (FRANKFURT: FMG) is pleased to announce that the Company has filed on SEDAR+ an independent Preliminary Economic Assessment (“PEA”) technical report (the “Report”) for its 100%-owned Duparquet Gold Project (“Duparquet” or the “Project”) located in the Abitibi region of Quebec, Canada.
The Report, entitled “NI 43-101 Technical Report: Preliminary Economic Assessment on the Duparquet Gold Project, Quebec, Canada” was prepared by G Mining Services Inc. of Montreal, Quebec (“G Mining”) in accordance with National Instrument 43-101 Standards of Disclosure for Mineral Projects (“NI 43-101”) and has an effective date of September 15, 2023.
The PEA results support a 15,000 tonnes per day open pit and underground mining operation over an 11-year mine life. Highlights include:
Note: Base case parameters assume a gold price of US$1,800/oz and an exchange rate (C$ to US$) of 1.33. All currencies are reported in Canadian dollars unless otherwise specified. NPV calculated as of the commencement of construction and excludes all pre-construction costs.
(1) Total Cash Costs consist of mining costs, processing costs, mine-level G&A, treatment and refining charges and royalties.
(2) AISC includes total cash costs plus sustaining capital, development capital and closure costs.
PEA Overview
The Duparquet Gold Project, located in the Abitibi region of Quebec, Canada, is one of the largest undeveloped gold projects in North America. The Project is located immediately north of the town of Duparquet which is approximately 50 kilometres northwest of Rouyn-Noranda, Quebec, a major mining service centre and home to the only remaining copper smelter in Canada. Duparquet currently hosts 3.4 million ounces of gold in the Indicated Mineral Resource category and 2.6 million ounces of gold in the Inferred Mineral Resource category, as set out in Table 4 in the Mineral Resource Estimate section.
The PEA evaluates recovery of gold from a 15,000 tonne-per-day (“tpd”) open pit and underground mining operation, with a process plant that includes crushing, grinding, and flotation, producing a concentrate for sale. The PEA only considers the Duparquet gold deposit located on the Beattie, Donchester, Central Duparquet and Dumico claim blocks and does not include the Pitt Gold and Duquesne deposits (see Mineral Resource Estimate section).
Table 1: Key PEA Assumptions and Project Economics (1)
Key Assumptions | Unit | LOM |
Gold Price | US$/oz | US$1,800/oz |
Exchange Rate | C$:US$ | 1.33 |
Production Profile | Unit | LOM |
Total Open Pit Tonnage | Mt | 282.0 |
Total Open Pit Mineralized Material Mined | Mt | 43.6 |
Open Pit Strip Ratio | w:o | 5.4 |
Total Underground Mineralized Material Mined | Mt | 12.0 |
Total Mineralized Material Mined from Historic Tailings | Mt | 4.1 |
Total Tonnes Processed | Mt | 59.7 |
Daily Throughput | tpd | 15,000 |
Mill Grade | g/t Au | 1.51 |
Mine Life | Years | 11 years |
Gold Recovery to Concentrate | % | 89.5% |
LOM Metal Recovered | koz Au | 2,595 koz Au |
Average Annual Recovered | koz Au | 233 koz Au |
Operating Costs (US$/oz) | Unit | LOM |
Total Cash Costs (2) | US$/oz | $751 |
AISC (3) | US$/oz | $976 |
Capital Expenditures | Unit | LOM |
Initial Capital | C$M | C$706 |
Sustaining and Development Capital | C$M | C$738 |
Closure Costs | C$M | $30 |
Estimated Salvage Value | C$M | ($36) |
Economics | Unit | LOM |
NPV at 5% (pre-tax; post-tax) | C$M | C$1,073; C$588 |
IRR (pre-tax; post-tax) | % | 24.9%; 18.0% |
Payback (pre-tax; post-tax) | Years | 3.8 years; 4.8 years |
Mineral Resource Estimate
In September 2022, the Duparquet Gold Project Mineral Resource Estimate (“MRE”) was updated by InnovExplo Inc. in accordance with NI 43-101. (See news release of September 12, 2022 for more details) The Duparquet Gold Project contains 3.44 million ounces of gold in the Measured & Indicated category, grading 1.55 g/t Au, and an additional 1.64 million ounces of gold in the Inferred category, grading 1.36 g/t Au (see Table 2).
In September 2023, new updated Mineral Resource Estimates were completed on First Mining’s 100% owned Pitt Gold and Duquesne projects and have added 1.0 million ounces of gold grading 2.32 g/t Au in the Inferred category (see Table 3), which will now form part of the larger consolidated Duparquet Gold Project. During the final validation and completion of the Report, minor adjustments were made to the Pitt Gold deposit MRE statement disclosed in the September 7, 2023 press release. The adjustments are presented in table 3 and 4 of this release for the Pitt Gold deposit and the consolidated 2023 MRE, respectively.
Following the updated Mineral Resource Estimate at Pitt Gold and Duquesne, the consolidated Duparquet Project now contains 3.44 million ounces of gold in the Measured & Indicated category, grading 1.55 g/t Au, and an additional 2.64 million ounces of gold in the Inferred category, grading 1.62 g/t Au.
Table 2: Duparquet Deposit Mineral Resource Estimate (Effective September 12, 2022)
Area (potential mining method) |
Cut-off (g/t) |
Measured resource | Indicated resource | Inferred resource | ||||||
Tonnage (t) | Au (g/t) |
Ounces | Tonnage (t) | Au (g/t) |
Ounces | Tonnage (t) | Au (g/t) |
Ounces | ||
Open Pit | 0.40 | 163,700 | 1.37 | 7,200 | 59,410,600 | 1.52 | 2,909,600 | 28,333,000 | 1.07 | 970,400 |
UG Mining | 1.50 | – | – | – | 5,506,900 | 2.26 | 399,300 | 9,038,900 | 2.29 | 665,600 |
Tailings | 0.40 | 19,900 | 2.03 | 1,300 | 4,105,200 | 0.93 | 123,200 | – | – | – |
Total | 183,600 | 1.43 | 8,500 | 69,022,700 | 1.55 | 3,432,100 | 37,371,900 | 1.36 | 1,636,000 |
Table 3: Pitt Gold (Adjusted) and Duquesne Deposits Mineral Resource Estimate (Effective September 15, 2023) (not included in the PEA)
Area (potential mining method) |
Cut-off (g/t) |
Pitt Gold Inferred Resource | Duquesne Inferred resource | ||||
Tonnage (t) | Au (g/t) |
Ounces | Tonnage (t) | Au (g/t) |
Ounces | ||
Open Pit | 0.50 | – | – | – | 6,300,000 | 1.56 | 316,000 |
UG Mining | 1.75 | 2,120,000 | 2.75 | 187.200 | 5,030,000 | 3.10 | 501,400 |
Total | 2,120,000 | 2.75 | 187.200 | 11,330,000 | 2.24 | 817,400 |
Table 4: Duparquet Gold Project Consolidated Mineral Resource Estimate (Effective August 31, 2023)*
Area (potential mining method) |
Total Measured Resource | Total Indicated Resource | Total Inferred Resource | ||||||
Tonnage (t) | Au (g/t) |
Ounces | Tonnage (t) | Au (g/t) |
Ounces | Tonnage (t) | Au (g/t) |
Ounces | |
Open Pit | 163,700 | 1.37 | 7,200 | 59,410,600 | 1.52 | 2,909,600 | 34,633,000 | 1.16 | 1,286,400 |
UG Mining | – | – | – | 5,506,900 | 2.26 | 399,300 | 16,189,000 | 2.60 | 1,354,100 |
Tailings | 19,900 | 2.03 | 1,300 | 4,105,200 | 0.93 | 123,200 | – | – | – |
Total | 183,600 | 1.43 | 8,500 | 69,022,700 | 1.55 | 3,432,100 | 50,822,000 | 1.62 | 2,640,500 |
*Refer to respective deposit resource estimate table for cut-off grade; adjusted for Pitt Gold
Notes to accompany the Duparquet Gold Project Mineral Resource Estimates:
Environment & Community
The PEA has considered and incorporated the opportunity to leverage the Duparquet Gold Project development with the reclamation of the brownfield site conditions including the removal and reprocessing of over 4.1 Mt of uncontained historical mine tailings. With such measures incorporated into the PEA mine plan, in combination with the ability of the Project to collect and treat historically impacted groundwater via the excavation and dewatering of the open pit, the Project is positioned to deliver both environmental and socio-economic benefits via employment, contracting and revenue for the Municipality of Duparquet. The PEA is anticipated to be refined and optimized based on consultation and input to be received by government, the Municipality of Duparquet and other local and regional stakeholders, and local First Nation community.
Since acquiring the Duparquet Gold Project in September of 2022, First Mining has prioritized meeting the people, communities and government representatives on project planning in an open and transparent manner. First Mining published the Mines d’Or Duparquet website to share project information and has recently finished renovations required to open a First Mining community relations office in Duparquet. The Project provides an opportunity to address historical environmental aspects at the Project site to improve long-term sustainability, economic activity and support sustainable municipal planning and development.
The Municipality of Duparquet is in the Abitibi-Témiscamingue region which has been shaped primarily by natural resource-based industries, including mining, and forestry, where the mining industry accounts for 1 in 7 jobs in the region.
Qualified Persons
The affiliation and areas of responsibility for each of the Qualified Persons involved in preparing the PEA are as follows:
Table 5: Qualified Persons for PEA NI 43-101
Qualified Persons | Company | Area of Expertise |
Carl Michaud, P.Eng. | G Mining Services Inc. | Operating Cost Estimation, Economic Analysis and Mine Engineering |
Alexandre Dorval, P. Eng. | G Mining Services Inc. | Open pit Mine Engineering |
Marina Iund. P.Geo. | InnovExplo Inc. | Duparquet MRE |
Olivier Vadnais-Leblanc, P.Geo. | InnovExplo Inc. | Duquesne and Pitt Gold MRE |
Carl Pelletier. P.Geo. | InnovExplo Inc. | Duparquet, Duquesne and Pitt Gold MRE |
Simon Boudreau, P. Eng. | InnovExplo Inc. | Duparquet, Duquesne and Pitt Gold MRE |
Neil Lincoln, P. Eng. | G Mining Services Inc. | Mineral Processing and Recovery Methods |
Philip Rodrigue, P. Eng. | G Mining Services Inc. | Infrastructure and Capital Cost Estimation |
Sheldon Smith MES, P. Geo | Stantec Consulting Ltd. | Environmental and Permitting |
The Company cautions that the results of the PEA are preliminary in nature and include Inferred Mineral Resources that are considered too speculative geologically to have the economic considerations applied to them that would enable them to be categorized as mineral reserves. There is no certainty that the results of the PEA will be realized.
Qualified Persons
Mr. Louis Martin P.Geo., (OGQ 0364), a consultant of First Mining, is a “Qualified Person” for the purposes of NI 43-101, and he has reviewed and approved the scientific and technical disclosure contained in this news release.
About First Mining Gold Corp.
First Mining is a gold developer advancing two of the largest gold projects in Canada, the Springpole Gold Project in northwestern Ontario, where we have commenced a Feasibility Study and permitting activities are on-going with a draft Environmental Impact Statement (“EIS”) for the project published in June 2022, and the Duparquet Project in Quebec, a PEA stage development project located on the Destor-Porcupine Fault Zone in the prolific Abitibi region. First Mining also owns the Cameron Gold Project in Ontario and a portfolio of gold project interests including the Pickle Crow Gold Project (being advanced in partnership with Auteco Minerals Ltd.), the Hope Brook Gold Project (being advanced in partnership with Big Ridge Gold Corp.), and a large equity interest in Treasury Metals Inc.
First Mining was established in 2015 by Mr. Keith Neumeyer, founding President and CEO of First Majestic Silver Corp.
ON BEHALF OF FIRST MINING GOLD CORP.
Daniel W. Wilton
Chief Executive Officer and Director
For further information, please contact:
Toll Free: 1 844 306 8827 | Email: info@firstmininggold.com
Paul Morris | Director, Investor Relations | Email: paul@firstmininggold.com
IBF4