Follow Us! Like Our Page!

Mountain Province Diamonds Announces Updated Life of Mine Plan and Updated Mineral Resource and Reserve Estimate

Press Release

TORONTO, Aug. 21, 2024 – Mountain Province Diamonds Inc. (TSX: MPVD) and (OTCQX: MPVD) (“Mountain Province”, or the “Company”) is pleased to announce today that it has completed an updated mineral reserve and mineral resource estimate and life of mine plan (the “LOM”) in respect of the Gahcho Kué Mine, a joint venture between De Beers Canada Inc. (51%) and Mountain Province (49%), located 280 km northeast of Yellowknife, Northwest Territories.  The updated LOM is the result of engineering work done to steepen the pit walls, resulting in realization of further value at the Gahcho Kué mine.

In accordance with National Instrument 43-101 – Standards of Disclosure For Mineral Projects (“NI 43-101”), a supporting technical report effective April 22, 2024 will be filed within 45 days of this news release (the “2024 Technical Report”). The 2024 Technical Report will supersede the technical report entitled “NI 43-101 Technical Report Gahcho Kué Mine Northwest Territories Canada” having an effective date of December 31, 2021 and a report date of March 28, 2022 (the “2022 Technical Report”).

Highlights

  • Mountain Province’s 49% share of operating cash flow from remaining open pit mining operations is estimated at $626 million.
  • Ore processing is now estimated to finish early 2031, not 2030 as estimated in the 2022 Technical Report.
  • On a full-year basis from 2024 to 2031 the total diamond recovery is estimated to be 36.3 million carats compared to 30.8 million carats in the 2022 Technical Report.

Mark Wall, the Company’s President and Chief Executive Officer, commented: “This is an important update to the production profile of the Gahcho Kué Mine. The projected operational after-tax cash flow attributable to Mountain Province for the balance of the open pit life of mine plan of $626 million demonstrates the value of the Gahcho Kué mine. The diamond market is considerably softer than the period when the previous 2022 Technical Report was completed, which creates upside opportunity to the economics should prices improve.

These economics exclude ‘inferred’ resources included in the new pit design.

The engineering work done to steepen the pit walls has resulted in ore that is deeper in the open pit coming into the mine plan in addition to a small reduction in waste stripping.

On a full-year basis for 2024 the updated Technical Report has the mine planning to produce 36.3 million carats (on a 100% basis) from the beginning of 2024 to the end of the life of mine, whereas the 2022 Technical Report had 30.8 million carats being produced from the beginning of 2024 to the end of the life of the mine.  Included in the production plan is moving to a lower Bottom Cut-off from 1.1mm to 1.0mm in 2027 which coincides with expected lower global production due to mine closures from 2026 onward.

I am pleased to update the market on the results of the engineering improvements to the mine.  We will continue to look for opportunities to optimize production and manage costs.”

Life of Mine

Updated geotechnical pit slope recommendations since the 2022 Technical Report allowed the various pits to be redesigned with steeper walls allowing additional kimberlite to be captured within the pits and an updated LOM plan.  The updated LOM plan extends production through 2031 and reflects an increase of 2.7 Mt at 2.0 c/t (5.5 Mcts), relative to the prior LOM plan.

Updated Mineral Resource and Reserve Estimate

There have been three block model updates for the Gahcho Kué Mine since the 2022 Technical Report, each of which have increased the overall volume of the ore bodies.  The interpretation of the external kimberlite contacts was updated based on mining data including blast holes logs and face mapping contact pickups. This information allowed projection/interpretation of changes to 3-4 benches below the current mining benches, providing a more probable view of kimberlite volumes to be mined in the short term. In addition, several drillholes from the Resource Extension Program were included in the update to Hearne and the surrounding country rock models.

Mineral Resource Estimate

Resource

Classification

Tonnes
(Mt)

Carats
(Mct)

Grade
(c/t)

5034

Indicated

6.9

15.0

2.16

Inferred

1.4

2.5

1.82

Hearne

Indicated

0.6

1.2

1.95

Inferred

1.5

2.8

1.82

Tuzo

Indicated

11.5

18.1

1.57

Inferred

10.3

18.4

1.78

Wilson

Indicated

2.3

2.1

0.89

Inferred

Summary (In-Situ)

Indicated

21.4

36.4

1.70

Inferred

13.3

23.7

1.79

Stockpiles

Indicated

3.3

2.4

0.73

Inferred

Grand Total Inclusive
Resource

Indicated

24.7

38.8

1.57

Inferred

13.3

23.7

1.79

Notes:

(1)  Mineral Resources are reported at a bottom cut-off of 1.0 mm. 

Mineral Resources are constrained within an optimized pit shell using a 1.6 revenue factor. Prices used to determine optimal pit shell varied by facies and ranged from 71 US$/ct to 146 US$/ct with an exchange rate of 1.30 CAD:USD. Process recovery of the diamonds was assumed to be 100% Operating costs used to determine the optimal pit shell include an open pit mining cost of 4.1 C$/t mined and a processing cost of C$72.0/t milled; 

(2)   Mineral Resources are not Mineral Reserves and do not have demonstrated economic viability. 

(3)   Tonnage quoted as dry metric tonnes.

(4)   Resources are inclusive of Indicated Resources that have been converted to Probable Reserves.

(5)   Resources have been depleted of any material that was processed prior to and including Apr 22,    2024.

(6)   MPD’s attributable portion of mineral resources is 49%.

Mineral Reserve Estimate

The mineral reserves for the Gahcho Kué Mine were updated with the new mine plan and updated mineral resource estimate and have an effective date of April 22, 2024.

Pipe

Classification

Tonnes
(Mt)

Carats
(Mct)

Grade
(c/t)

5034

Probable

6.1

12.3

2.01

Hearne

Probable

0.3

0.5

1.54

Tuzo

Probable

11.3

17.3

1.52

Wilson

Probable

2.5

2.1

0.84

In-Situ Total

Probable

20.3

32.1

1.59

Stockpile

Probable

3.3

2.4

0.73

Total

Probable

23.6

34.6

1.47

Notes:

(1)  Mineral Reserves are reported within detailed designed pits and confirmed to have a positive economic return.   Economic evaluation is based a LOM production schedule using an average diamond price of $US95/ct, a process recovery of 100%, an exchange rate of 1.30 CAD:US, a mining opex of $5.9/t mined, a processing opex of $58.5/t milled.

(2)   Mineral Reserves are reported at a variable bottom cut-off (BCO) based on the LOM production schedule.  A BCO of 1.1 mm is used for 2024-2026, and a BCO of 1.0 mm is used for 2027-2031.

(3)   Mineral Reserves have been depleted to account for mining and processing activity prior to and including Apr 22, 2024.

(4)   Mineral Reserves are based upon the updated resource model (2024) and therefore reflect any changes to the estimation    of tonnes, grade and contained carats within that resource.

(5)    Mineral Reserves may be subject to legal, political, environmental and other risks and uncertainties. See Cautionary Note Regarding Forward-Looking Statements.  The QP is not aware of any legal, political, environmental or other risk factors that might materially affect the estimate of Mineral Reserves.

(6)    CIM definitions were followed for Mineral Reserves.

(7)   Tonnages are rounded to the nearest 100,000 t, diamond grades are rounded to one decimal place to properly reflect the Reserve estimate accuracy.

(8)    Tonnage and grade measurements are in metric units; contained diamonds are reported as millions of carats.

(9)     MPD’s attributable portion of mineral reserves is 49%.

Technical Information and Technical Report Filing

The Mineral Resource and Mineral Reserve estimates for the Gahcho Kué Mine and the other scientific and technical information contained in this news release was prepared by Tysen Hantelmann and Mike Makarenko, each a Qualified Persons (“QP”), as defined in NI 43-101 and independent of the Company. Data verification processes undertaken in the previous Technical Reports have been reviewed. The QPs are of the opinion that the data verification is adequate for use in the 2024 Technical Report.

The 2024 Technical Report will be filed under the Company’s profile on SEDAR+ at www.sedarplus.ca within 45 days of this news release. Readers are encouraged to read the 2024 Technical Report in its entirety, including all qualifications, assumptions, exclusions and risks that relate to the Mineral Resource, Mineral Reserves and LOM. The 2024 Technical Report is intended to be read as a whole, and sections should be read or relied upon out of context.

About the Company

Mountain Province Diamonds is a 49% participant with De Beers Canada Inc.  in the Gahcho Kué diamond mine located in Canada’s Northwest Territories. The Gahcho Kué Joint Venture property consists of several kimberlites that are actively being mined, developed, and explored for future development. The Company also controls approximately 112,000 hectares of mineral claims and leases surrounding the Gahcho Kué Mine that include an Indicated mineral resource for the Kelvin kimberlite and Inferred mineral resources for the Faraday kimberlites.

For further information: FOR FURTHER INFORMATION, PLEASE CONTACT: Mark Wall, President, and CEO, 151 Yonge Street, Suite 1100, Toronto, Ontario M5C 2W7, Phone: (416) 361-3562, E-mail: info@mountainprovince.com

IBF4

Loading

NationTalk Partners & Sponsors Learn More