Press Release
MONTREAL, May 24, 2022 – Osisko Development Corp. (“Osisko Development” or the “Company”) (TSX.V-ODV) is pleased to announce the results from its Preliminary Economic Assessment (“PEA” or the “Study”) completed by BBA Engineering Ltd., consultants for the Cariboo Gold Project (“Cariboo” or the “Project”) in Central British Columbia (“BC”).1
The PEA provides a technical and economic update based on the updated underground Mineral Resource Estimate (“MRE”) from the 2021 diamond drill campaign and current costs and economic estimates. The MRE contains 27.1 million tonnes (“Mt”) at an average grade of 4.0 grams per tonne gold (“g/t Au”) for a total of 3.47 million ounces (“M oz”) in the Measured and Indicated Category (consisting of a Measured Resource of eight thousand ounces of gold (47,000 tonnes grading 5.1 g/t Au) and an Indicated Resource of 3.46 million ounces of gold (27 million tonnes grading 4.0 g/t Au)) and 14.4 Mt at a grade of 3.5 g/t Au for a total of 1.6 M oz in the Inferred category (Table 6). These mineral resources have informed an 8,000 tonnes per day (“tpd”) scenario over a 12-year operating mine life, which highlights the potential growth of the Cariboo Gold Project. The PEA is available on the Company’s website and the profile of the Company at www.sedar.com. The Company notes that mineral resources are not mineral reserves as they do not have demonstrated economic viability. The Company notes that a preliminary economic assessment is preliminary in nature, it includes inferred mineral resources that are considered too speculative geologically to have economic consideration applied to them that would enable them to be categorized as mineral reserves, and there is no certainty that the preliminary economic assessment will be realized.
The PEA illustrates potential economics for a low cost, large scale, underground gold mine, with industry leading operating costs. The study outlines total gold production of 2.8 million gold ounces, resulting in an average annual gold production profile of 236,000 ounces with an All-In- Sustaining Cost (“AISC”) per ounce of $1,222 (US$962) (AISC is a non-IFRS measure – please see under the heading “Non- IFRS Measures” below). The Project after-tax net present value (“ NPV”) (5% discount rate) is $764 million with an after-tax internal rate of return (“IRR”) of 21.4% at a gold price of $2,223 (US$1,750) per ounce, and $912 million and 24.5% at a spot gold price for May 19, 2022 at $2,343 (US$1,845) per ounce.
The PEA recommends that the Company continues to work towards a feasibility study and completes the following steps:
The Company plans to proceed with a feasibility study in connection with the work plan recommended by the PEA.
The Company advises that this clarifying news release is being issued at the request of the Autorité des marchés financiers following a continuous disclosure review. Certain previous economics described in the Table 1 below in relation to the Project disclosed by the Company were not supported by a technical report prepared in accordance with National Instrument 43-101 Standards of Disclosure for Mineral Projects (“NI 43-101”) and are superseded by the economics set out in the current NI 43-101 report and the Company cautions the reader not to rely on such previous economics. The Company is also filing a restated version of its annual managements’ discussion and analysis and annual information form to, as applicable, remove the unsupported technical information and qualify other disclosure.
The previous economics were made public by the Company in connection with the environmental assessment for the Cariboo Project. These economics were prepared in accordance with the requirements for major projects in British Columbia to be assessed for potential environmental, social, economic, health and cultural effects by the Environmental Assessment Office, as required by the Environmental Assessment Act (British Columbia) (the “Environmental Assessment Act”) . The previous economics do not include numbers verified to a NI 43-101 standard, and do not include the suite of investor focused economics, including the IRR and NPV for the project. These previous economics were to engineering standards. You will find below a table showing the differences between the previous economics and the economics contained in the PEA.
Table 1: Project Economics
Information | Previous economics | PEA economics | Explanation of the | ||||
differences | |||||||
Production Rate (tpd) | 4,750 tpd | Up to 8,000 tpd | Based on the Company’s | ||||
initial expectation a 4,750 | |||||||
tpd mine was used for the | |||||||
environmental | |||||||
assessment but in | |||||||
accordance with the | |||||||
MRE, its is expected that | |||||||
production could increase | |||||||
during the life of the mine | |||||||
to up to 8,000 tpd | |||||||
Mine Life | 16 years | 12 years | Higher production rate | ||||
Initial Capital Cost and | Projected initial capital | Projected initial | The differences are | ||||
Total Capital Cost | cost of $400 to $450 | capital cost of $122 | influenced by number of | ||||
million and total capital | million, expansion | factors including: | |||||
cost over the life of | capital cost of $716 | ||||||
mine estimated at just | million and total | | higher production | ||||
under $900 million | capital over the life | rate | |||||
of mine estimated at | | additional | |||||
$1,364 million | |||||||
resources | |||||||
| additional | ||||||
environmental | |||||||
and engineering | |||||||
data | |||||||
| inflation. | ||||||
The Key Operational Findings of the PEA are:
expansion raising the throughput at 8,000 tpd
o Projected to have an initial mine life of 12 years
The Key Financial Forecast of the PEA are (at a base case gold price of US$1,750/oz):
o After-tax NPV (5%) of $764M o After-tax IRR of 21.4%
Sean Roosen, Chair & Chief Executive Officer of Osisko Development, commented: “The PEA builds on previous technical work while incorporating the results of extensive drilling together with several improvements and optimizations. The capital and operating cost estimates rely on recent budgetary quotes reflecting the current cost environment and our project execution approach. The recent inflation and difficulty with the supply chain has put to the forefront the challenges the mining industry is facing. The Project provides an attractive potential gold production profile of approximately 297,000 ounces per year when operating at 8,000tpd over an 8-year period, making it one of the premier gold development projects in North America and key socio-economic contributor to the Cariboo region, particularly in Wells, Quesnel, and surrounding areas, and the Province of BC. This PEA highlights a phased approach with an initial project able to produce 75,000oz/year at low capital cost, but most importantly, providing us access to the deposits from underground to do further exploration and seek to unlock more potential value outside of the current mine design that has an average mine depth of 350 meters. We believe this is a more prudent approach in the actual economic context without compromising the full potential of the Cariboo Gold Project.”
Table 2: Key Economic Outputs of the Study
Description | Units | ||||
Production Date (Operations Period) | |||||
Mine Life | year | 12 | |||
Average Process Throughput | tpd | 6,424 | |||
Average Process Throughput | MMt2/ year | 2,346 | |||
Gold Head Grade | g/t | 3.40 | |||
Contained Gold | koz3 | 3,080 | |||
Recovery | % | 92.1 | |||
Total Gold Production | koz | 2,837 | |||
Average Annual Gold Production | koz | 236,000 | |||
Average Annual Full Years at 8,000tpd | koz | 297,000 | |||
Operating Costs (Average LOM) | |||||
Mining Cost | $/t mined | 52.73 | |||
Processing Cost | $/t mined | 24.00 | |||
Concentrate transport | $/t mined | 3.85 | |||
Tailings and Water Management | $/t mined | 5.81 | |||
G&A Cost | $/t mined | 7.63 | |||
Total Site Operating Costs | $/t mined | 94.02 | |||
Total Site Operating Costs | US$/oz | 734.85 | |||
AISC | US$/oz | 961.6 | |||
Capital Costs | |||||
Initial Capital | $ MM | 121.5 |
Expansion Capital | $ MM | 716.1 |
Life of Mine Sustaining Capital | $ MM | 527.2 |
Total Capital Costs | $ MM | 1,364.84 |
Financial Evaluation | ||
Gold Price Assumption | US$/oz | 1,750 |
USD:CAD FX Assumption | x | 1.27 |
After-Tax NPV (5%) | $ MM5 | 763.8 |
After-Tax IRR | % | 21.4 |
Payback | year | 5.8 |
Read More: https://osiskodev.com/wp-content/uploads/2022/05/ODV-Cariboo-PEA-PR-May-24-2022-Final_18373907_1.pdf
IBF4
128 total views, 2 views today