Toronto, Ontario–(Newsfile Corp. – February 5, 2024) – Seabridge Gold (TSX: SEA) (NYSE: SA) announced today updated Mineral Resource Estimates for the Iron Cap and Kerr deposits at its 100-owned KSM Project located in northwestern British Columbia. The underground block cave constraining shapes for Kerr and Iron Cap have been updated using the same metal prices used in the 2022 Mitchell and East Mitchell open pit constraining shapes (US$1,820/oz Au, US$4.20/lb Cu, US$28/oz Ag, and US$ 13.5/lb Mo at a currency exchange rate of 0.83 US$ per 1.00 CDN).
Inferred Mineral Resources increase by 5.9 Million Ounces of Gold, 3.3 Billion Pounds of Copper, 55.4 Million ounces of Silver and 51 million pounds of molybdenum.
Indicated Mineral Resources increase by 0.3 Million Ounces of Gold, 0.2 Billion Pounds of Copper, 3.5 Million ounces of Silver and 2 million pounds of molybdenum.
The updated Mineral Resource Estimates within the underground block cave constraining shapes for Kerr and Iron Cap have a mining grade shut-off applied which is appropriate for the assumed block cave mining method. This is consistent with the unselective block cave mining method used in the 2022 PEA and is different from previous Mineral Resource statements at Kerr and Iron Cap which applied a grade cut-off.
Resource models supporting the updated Mineral Resource Estimates have not changed and they are the same models used in the previous resource statement as reported in the KSM Preliminary Feasibility Study and Preliminary Economic Assessment, NI 43-101 Technical Report”, with an effective date of August 08, 2022 (see here).
Seabridge Chairman and CEO Rudi Fronk said the resource restatements reflect gains from a consistent application of metal price parameters. “As we move towards a joint venture on KSM, it makes sense to normalize our resource estimates across all of KSM’s deposits.
The mineral resources within the 2022 PEA mine plans for Kerr and Iron Cap are subsets of, and consistent with, the updated Mineral Resources, and the mineral resources within the PEA mine plan are not impacted by the updated underground block cave constraining shapes.
The changes to the Mineral Resources are not a result of any changes to the resource models, but rather using a shut-off grade strategy for the Kerr and Iron Cap underground resources and aligning the metal price assumptions for the constraining shapes with other deposits on the KSM Project. The 2022 PEA mine plan is a subset to the mineral resources at Kerr and Iron Cap and is not impacted by the change to Mineral Resources. The increased mineral resources compared to the previous estimate would only be mined after the 33 years of mine life based on the open pit Mineral Reserves. Any future cash flows resulting from these additional mineral resources is not considered material. The change in Mineral Resource is considered not material to the KSM Project or to Seabridge Gold.
Updated Mineral Resources and the unchanged Mineral Reserves for the full KSM property are appended to the end of this news release and can be viewed on the Seabridge website at www.seabridgegold.com and here.
Qualified Persons
Henry Kim P.Geo., the independent Qualified Person and Principal Resource Geologist with Wood Canada Limited, has reviewed and approved the scientific and technical information contained in this press release. Details of the data verification performed to support the Mineral Resource estimates, and identification of any known legal, political, environmental, or other risks that could materially affect the potential development of the mineral resources are provided in Technical Report dated August 8, 2022.
About Seabridge Gold
Seabridge holds a 100% interest in several North American gold projects. Seabridge’s principal asset, the KSM project, and its Iskut projects are located in Northwest British Columbia, Canada’s “Golden Triangle”, the Courageous Lake project is in Canada’s Northwest Territories, the Snowstorm project in the Getchell Gold Belt of Northern Nevada, and the 3 Aces project is in the Yukon Territory. For a full breakdown of Seabridge’s Mineral Reserves and Mineral Resources by category please visit the Seabridge’s website at http://www.seabridgegold.com.
Neither the Toronto Stock Exchange, New York Stock Exchange, nor their Regulation Services Providers accepts responsibility for the adequacy or accuracy of this release.
Cautionary note to U.S. Investors concerning estimates of Mineral Reserves and Mineral Resources
All mineral reserve and resource estimates reported by Seabridge were estimated in accordance with the Canadian National Instrument 43-101 and the Canadian Institute of Mining, Metallurgy and Petroleum (“CIM”) Definition Standards (May 10, 2014). Since 2021 the U.S. Securities and Exchange Commission (“SEC”) recognizes estimates of “measured mineral resources,” “indicated mineral resources” and “inferred mineral resources” and uses new definitions of “proven mineral reserves” and “probable mineral reserves” and the supporting mining studies that are substantially similar to the corresponding CIM Definition Standards. However, the CIM Definition Standards differ from the requirements applicable to US domestic issuers. Further, “inferred mineral resources” are that part of a mineral resource for which quantity and grade are estimated on the basis of limited geologic evidence and sampling. Mineral resources which are not mineral reserves do not have demonstrated economic viability.
ON BEHALF OF THE BOARD
“Rudi Fronk”
Chairman & C.E.O.
For further information please contact:
Rudi P. Fronk, Chairman and C.E.O.
Tel: (416) 367-9292 • Fax: (416) 367-2711