March 23, 2022
Monthly Highlights
Making headway before spring breakup
With over 3,500 workers on- site, construction activities steadily progress as we head into spring breakup – the time of year when field construction work is reduced due to soft, thawing ground conditions caused by melting snow. In Section 1, critical in-stream work has been completed at the Coldstream Creek water crossing. As for the Wilde Lake Compressor Station, the team celebrated a significant milestone with the completion of initial alignment for all three compressor units. Overall construction at the Wilde Lake Compressor Station has surpassed 74 per cent; the facility is expected to be completed by the beginning of 2023. Over in Section 4, our team welcomed the safe removal of the temporary free-span Stuart River bridge. The Stuart River bridge saved an estimated 6.3 million kilometres of project vehicle traffic during service.