Press Release
Vancouver, BC (March 31, 2026) Skeena Resources Limited (TSX: SKE, NYSE: SKE) (“Skeena Gold & Silver”, “Skeena” or the “Company”) is pleased to provide an update on the advancement of its 100% owned Eskay Creek Gold-Silver Project (“Eskay” or the “Project”) in Northwest British Columbia. Since commencing development activities in December 2024, the Company has achieved notable progress advancing Eskay Creek. As of February 28, 2026, the Project was 49% complete, with 66% of total project costs now contractually committed. Initial production at Eskay Creek remains on schedule, targeted for the second quarter of 2027 and commercial production expected in the third quarter.
Randy Reichert, President & Chief Executive Officer of Skeena, commented, “Our strategy of initiating development activities well ahead of final permit receipt has delivered meaningful value for our shareholders. By acting early, we reduced project timeline risk and minimized inflationary impacts across key scopes by securing procurement contracts earlier. Having completed the permitting process and reaching the midway mark on construction, we felt it was important to provide a project update and show how far the project has advanced.”
Updated Construction Cost Estimate
Following receipt of the Environmental Assessment Certificate (“EA”) and joint provincial permits (see news release dated February 3, 2026), Skeena completed a comprehensive review of the permit conditions and the Project’s construction cost estimate. The Updated 2026 Construction Budget now incorporates final permit conditions, updated Impact Benefit Agreement (“IBA”) commitments, inflationary impacts, and learnings from early-stage construction, resulting in a more current and reliable estimate of the Project’s overall cost requirements. All references to dollars ($) in this news release are in United States (“US”) dollars.
The project cost outlined in the 2023 Definitive Feasibility Study (“DFS”) was US$560 million[1]. The updated cost estimate for the Project is US$659 million[2], both estimates are inclusive of approximately US$35 million in cost contingency. This represents an increase of US$99 million as compared to the 2023 DFS estimate.
The revised estimate incorporates updated project scope, engineering refinement, permitting conditions, IBA commitments, and project sanction/completion timing adjustments. The estimate also incorporates the use of leasing arrangements for portions of certain infrastructure, including the water treatment plant, high-voltage electrical infrastructure, and camp facilities, which have reduced the upfront construction cost requirements by approximately US$94 million.
Comprehensive reviews undertaken by the Project team, together with independent third‑party consultants, continue to support the development schedule. In tandem with the updated 2026 construction budget, the project remains on schedule, with initial production targeted for Q2 2027 followed by commercial production in the third quarter.
Prior to receipt of final permits, and in anticipation of major construction activities, Skeena strategically advanced and de‑risked the Project throughout 2024 and 2025. As a result, as of December 31, 2025, the Company had invested approximately US$305 million in development expenditures and meaningfully progressed key construction scopes. As of December 31, 2025, the remaining development expenditures required to achieve initial production are estimated at US$354 million (net of planned US$94 million leasing arrangements), representing peak construction spending in 2026 of approximately US$291 million, with the balance of US$63 million expected to be incurred in 2027 as the Project transitions into commissioning.
Major construction highlights are summarized below, as of February 28, 2026.
| Area | Status | Progress as of February 28, 2026 |
| Process Plant Detailed Engineering | On Schedule | 92% complete and fully in support of construction activities; forecast to finish in April 2026. |
| Procurement | On Schedule | 88% of costs committed, with fabrication and receipt of key equipment and materials fully in support of construction activities. |
| Process Plant Construction | On Schedule | 46% complete, with the concentrator building and critical path concrete now complete. Mechanical installation has now commenced and is proceeding per schedule. |
| Initial Large Mining Equipment | Completed | Mobilization and commissioning of initial large mining equipment to support larger scale mining in the open pit was completed in H1 2025. |
| Open Pit Mining | On Schedule | Mining activities advanced in both 2024 and 2025 supporting pre-strip material movement for orebody access and production of material for construction purposes. Material mined to date totals 3 million tonnes. |
| Electrical Infrastructure Construction | On Schedule | Progressing per plan, with tap-in to the BC Hydro grid complete, earthworks and concrete complete at the Volcano Creek substation, and approximately 50% of the overhead power line to site complete. |
| Water Treatment & Management Construction | On Schedule | Significant progress of water management infrastructure, including installation and dry commissioning complete for the Stage 1 Water Treatment Plant. Excavation of MRSA Water Collection Pond was completed late 2025. |
| Permanent Camp Construction | On Schedule | Cleared and mass earthworks complete, with fabrication well advanced, utilities installation in progress, and full occupancy on track for July 2026. |
| Tailings Facility Construction (“TMSF”) | On Schedule | Initial haul road access to the tailings facility was completed in H2 2025 to support 2026 dam construction. |
| Assay Lab Construction | Completed | Construction and commissioning of the on-site Assay Lab was completed in 2024. The Assay Lab has now been operating successfully on site for 2 years. |
| Process Plant Pad Mass Earthworks | Completed | Completed late 2024. |
| Access Road Bridge Replacements | Completed | Both required bridge replacements on the mine access road were completed in H1 2025. |
Below is a summary of the main items contributing to the increase in the updated project cost estimate:
Remaining Construction Scopes
Below is a summary of the remaining construction activities that are required to commence pre-production:
About Skeena
Skeena is a leading precious metals development company focused on advancing the Eskay Creek Gold-Silver Project in British Columbia’s Golden Triangle. With the Project fully permitted and under construction, the Company is progressing Eskay Creek towards initial production and cash flow in the second quarter of 2027. Once in operation, Eskay Creek is expected to be one of the world’s highest-grade and lowest-cost open-pit precious metals mines, with significant silver by-product production that exceeds the output of many primary silver mines. Skeena is committed to responsible and sustainable mining in partnership with Indigenous communities, while maximizing the value of its mineral resources to generate long-term shareholder returns.
On behalf of the Board of Directors of Skeena Gold & Silver,
Walter Coles
Executive Chairman
Randy Reichert
President & CEO
For further information, please contact:
Galina Meleger
Vice President Investor Relations
E: info@skeenagold.com
T: 604-684-8725
W: www.skeenagoldsilver.com
IBF4
![]()