Follow Us! Like Our Page!

Skeena Gold & Silver Confirms Eskay Creek Reaches 49% Completion & Provides Project Update; Initial Production Remains on Schedule for Q2 2027

Press Release

Vancouver, BC (March 31, 2026) Skeena Resources Limited (TSX: SKE, NYSE: SKE) (“Skeena Gold & Silver”, “Skeena” or the “Company”) is pleased to provide an update on the advancement of its 100% owned Eskay Creek Gold-Silver Project (“Eskay” or the “Project”) in Northwest British Columbia. Since commencing development activities in December 2024, the Company has achieved notable progress advancing Eskay Creek. As of February 28, 2026, the Project was 49% complete, with 66% of total project costs now contractually committed. Initial production at Eskay Creek remains on schedule, targeted for the second quarter of 2027 and commercial production expected in the third quarter.

Randy Reichert, President & Chief Executive Officer of Skeena, commented, “Our strategy of initiating development activities well ahead of final permit receipt has delivered meaningful value for our shareholders. By acting early, we reduced project timeline risk and minimized inflationary impacts across key scopes by securing procurement contracts earlier.  Having completed the permitting process and reaching the midway mark on construction, we felt it was important to provide a project update and show how far the project has advanced.”

Updated Construction Cost Estimate
Following receipt of the Environmental Assessment Certificate (“EA”) and joint provincial permits (see news release dated February 3, 2026), Skeena completed a comprehensive review of the permit conditions and the Project’s construction cost estimate. The Updated 2026 Construction Budget now incorporates final permit conditions, updated Impact Benefit Agreement (“IBA”) commitments, inflationary impacts, and learnings from early-stage construction, resulting in a more current and reliable estimate of the Project’s overall cost requirements. All references to dollars ($) in this news release are in United States (“US”) dollars.

The project cost outlined in the 2023 Definitive Feasibility Study (“DFS”) was US$560 million[1]. The updated cost estimate for the Project is US$659 million[2], both estimates are inclusive of approximately US$35 million in cost contingency. This represents an increase of US$99 million as compared to the 2023 DFS estimate.

The revised estimate incorporates updated project scope, engineering refinement, permitting conditions, IBA commitments, and project sanction/completion timing adjustments. The estimate also incorporates the use of leasing arrangements for portions of certain infrastructure, including the water treatment plant, high-voltage electrical infrastructure, and camp facilities, which have reduced the upfront construction cost requirements by approximately US$94 million.

Comprehensive reviews undertaken by the Project team, together with independent third‑party consultants, continue to support the development schedule.  In tandem with the updated 2026 construction budget, the project remains on schedule, with initial production targeted for Q2 2027 followed by commercial production in the third quarter.

Prior to receipt of final permits, and in anticipation of major construction activities, Skeena strategically advanced and de‑risked the Project throughout 2024 and 2025. As a result, as of December 31, 2025, the Company had invested approximately US$305 million in development expenditures and meaningfully progressed key construction scopes. As of December 31, 2025, the remaining development expenditures required to achieve initial production are estimated at US$354 million (net of planned US$94 million leasing arrangements), representing peak construction spending in 2026 of approximately US$291 million, with the balance of US$63 million expected to be incurred in 2027 as the Project transitions into commissioning.

Major construction highlights are summarized below, as of February 28, 2026.

Area Status Progress as of February 28, 2026
Process Plant Detailed Engineering On Schedule 92% complete and fully in support of construction activities; forecast to finish in April 2026.
Procurement On Schedule 88% of costs committed, with fabrication and receipt of key equipment and materials fully in support of construction activities.
Process Plant Construction On Schedule 46% complete, with the concentrator building and critical path concrete now complete.  Mechanical installation has now commenced and is proceeding per schedule.
Initial Large Mining Equipment Completed Mobilization and commissioning of initial large mining equipment to support larger scale mining in the open pit was completed in H1 2025.
Open Pit Mining On Schedule Mining activities advanced in both 2024 and 2025 supporting pre-strip material movement for orebody access and production of material for construction purposes. Material mined to date totals 3 million tonnes.
Electrical Infrastructure Construction On Schedule Progressing per plan, with tap-in to the BC Hydro grid complete, earthworks and concrete complete at the Volcano Creek substation, and approximately 50% of the overhead power line to site complete.
Water Treatment & Management Construction On Schedule Significant progress of water management infrastructure, including installation and dry commissioning complete for the Stage 1 Water Treatment Plant. Excavation of MRSA Water Collection Pond was completed late 2025.
Permanent Camp Construction On Schedule Cleared and mass earthworks complete, with fabrication well advanced, utilities installation in progress, and full occupancy on track for July 2026.
Tailings Facility Construction (“TMSF”) On Schedule Initial haul road access to the tailings facility was completed in H2 2025 to support 2026 dam construction.
Assay Lab Construction Completed Construction and commissioning of the on-site Assay Lab was completed in 2024. The Assay Lab has now been operating successfully on site for 2 years.
Process Plant Pad Mass Earthworks Completed Completed late 2024.
Access Road Bridge Replacements Completed Both required bridge replacements on the mine access road were completed in H1 2025.

Below is a summary of the main items contributing to the increase in the updated project cost estimate:

  • General cost escalation reflecting inflationary pressures across labour, materials, and construction services.
  • In 2024 and 2025, the BC water discharge standards were changed and certain elemental limits were reduced to the lowest levels in the world. In addition, through Tahltan participation in the environmental assessment process, Tahltan values were incorporated into the site requirements. Enhanced water management and treatment infrastructure was required to meet final EA approval conditions and updated regulatory standards, including incorporation of environmental protection measures and community values identified through the assessment process.
  • Optimization of the permanent camp location to accommodate the ultimate Tailings Storage Facility configuration, resulting in associated design adjustments and site development costs.
  • Operational design enhancements implemented following the DFS to improve reliability, safety, and winter operating conditions, including:
    • Structural improvements to the mill building to improve snow management and operational safety
    • Conversion from a crushed ore storage bin to a covered conical stockpile to reduce freezing risk and improve material handling reliability
    • Improvements to concentrate dewatering capacity, including thickener sizing and filter configuration
    • Improvements to plant HVAC and dust control systems
  • Updated pricing and scope refinement for high-voltage electrical infrastructure and the Volcano Creek substation following detailed engineering and procurement, reflecting global demand for electrical equipment and additional earthworks requirements.
  • Additional procurement and contracting costs associated with community participation and partnership commitments under the project’s Impact Benefit Agreement
  • Schedule extension of approximately six months to align construction sequencing with final permitting approvals. For greater certainty, this extension was already incorporated in the updated project timelines disclosed in the Company’s news release dated June 25, 2024 on project financing.

Remaining Construction Scopes
Below is a summary of the remaining construction activities that are required to commence pre-production:

  • Continuance of open pit mining to produce construction rock and, in Q4, commence ore mining and stockpiling
  • Widening of haul road to TMSF to support future dam construction and sub-aqueous PAG deposition
  • Completion of the stage 1 TMSF dam to enable future tailings deposition
  • Continuance of water management infrastructure including ponds and diversions, and completion of the first and second stage of the water treatment plants
  • Substantial completion of construction activities in the processing facilities
  • Mechanical completion testing and pre-commissioning activities in the processing facilities
  • Completion of construction of the Volcano Creek substation, 69 kV overhead power line to site, and Eskay Creek substation
  • Energization of processing facilities, water treatment plant, and other key facilities with permanent grid power
  • Completion of construction of the permanent camp

About Skeena

Skeena is a leading precious metals development company focused on advancing the Eskay Creek Gold-Silver Project in British Columbia’s Golden Triangle. With the Project fully permitted and under construction, the Company is progressing Eskay Creek towards initial production and cash flow in the second quarter of 2027. Once in operation, Eskay Creek is expected to be one of the world’s highest-grade and lowest-cost open-pit precious metals mines, with significant silver by-product production that exceeds the output of many primary silver mines. Skeena is committed to responsible and sustainable mining in partnership with Indigenous communities, while maximizing the value of its mineral resources to generate long-term shareholder returns.

On behalf of the Board of Directors of Skeena Gold & Silver,

Walter Coles
Executive Chairman

Randy Reichert
President & CEO

For further information, please contact:
Galina Meleger
Vice President Investor Relations
E:  info@skeenagold.com
T: 604-684-8725
W: www.skeenagoldsilver.com

IBF4

Loading

NationTalk Partners & Sponsors Learn More