Press Release
October 31, 2018, Vancouver, BC – Taseko Mines Limited (TSX: TKO; NYSE American: TGB) (“Taseko” or the “Company”) reports earnings from mining operations before depletion and amortization* of $33.7 million and adjusted net income* of $1.5 million for the three months ended September 30, 2018.
Russell Hallbauer, President & CEO commented, “In August, Gibraltar’s mine engineering group determined that the Granite Pit high wall could be steepened, based on data from geotechnical and rock structure evaluations. We immediately redesigned the Granite Pit pushback, which allowed us earlier access to high grade ore benches. These benches, which we partially mined in the third quarter, were not included in the 2018 mine plan and ended up having a dramatic impact on copper production during the quarter.”
“Not only did we benefit from higher grade ore in the third quarter, but the ore that was processed was also softer and we were able to achieve higher than design throughput of 87,000 tons per day, 6% higher than the previous quarter. The combination of higher grade ore and throughput resulted in 43 million pounds of copper production in the third quarter,” added Mr. Hallbauer.
Mr. Hallbauer continued, “Sales of 29 million pounds in the quarter were below production due to extremely poor rail service, which stranded 18.5 million pounds of copper in concentrate at the mine. The lower sales affected our quarterly revenues by approximately $40 million and cash flow by approximately $30 million, based on current copper pricing.”
“We continued to make progress at our Florence Copper Project during the quarter. The wellfield, SX/EW plant and all associated infrastructure are now commissioned and pre-operations tests are being performed with positive results to-date. We anticipate final authorizations to commence operations from the regulators shortly, and are ready to immediately commence leaching operations. This project represents many near-term catalysts for the Company as we demonstrate the low-cost, environmental and technical attributes of the in-situ production process,” continued Mr. Hallbauer.
“Fourth quarter production is expected to be at a more normalized level, with estimated total copper production of 130 million pounds for 2018. We anticipate that during the fourth quarter the railway will be able to move most of the excess copper concentrate inventory, in addition to the fourth quarter production, to the port for shipping. Depending on vessel scheduling and berth availability, we could realize sales of approximately 45 million pounds (100% basis) for the quarter,” concluded Mr. Hallbauer.
Third Quarter Highlights
IBF4
![]()