Press Release
VANCOUVER, British Columbia, Jan. 17, 2019 — Trevali Mining Corporate (“Trevali” or the “Company”) (TSX:TV; BVL: TV; OTCQX: TREVF; Frankfurt: 4TI) reports preliminary fourth quarter (“Q4”) and 2018 full year production and sales results, and provides its production, cash costs, and capital and exploration expenditure guidance for 2019.
Dr. Mark Cruise, Trevali’s President and CEO stated, “2018 was an eventful year for Trevali. It was the Company’s first full year operating in Africa and we successfully increased production at both Perkoa and Rosh Pinah over 2017 levels and are on track to extend mine lives through our focus on exploration. Despite the challenges faced at Caribou, Trevali produced 407 million lbs of payable zinc in 2018, in-line with our initial guidance set out one year ago. Heading into 2019, the Company continues to drive forward on creating value through exploration, evaluating ways to reduce costs and maximize production and looks forward to delivering increased shareholder value.”
Key highlights include:
| Table 1: Preliminary Consolidated Q4-2018 Production Results | ||||
| Three months ended December 31 |
Twelve months ended December 31 |
|||
| 2018 | 2017 | 2018 | 2017(1) | |
| Tonnes mined | 723,384 | 832,878 | 3,253,617 | 2,128,018 |
| Tonnes milled | 737,496 | 818,690 | 3,300,948 | 2,250,464 |
| Payable production: Zinc (million pounds) Zinc (tonnes) Lead (million pounds) Lead (tonnes) Silver (thousand ounces) |
102.7 46,562 9.7 4,406 285 |
104.8 47,530 13.5 6,103 397 |
406.9 184,545 41.7 18,915 1,171 |
225.1 102,122 45.8 20,790 1,562 |
(1) Twelve months ending December 31, 2017 consolidated preliminary production includes only September 1 to December 31, 2017 for Rosh Pinah and Perkoa. Trevali acquired the Perkoa and Rosh Pinah mines on August 31, 2017.
(2) Please refer to “Use of Non-IFRS Financial Performance Measures” below.
Perkoa Mine, Burkina Faso
Perkoa delivered a strong performance in 2018 with annual production of 184 million pounds, materially above the Company’s initial target of 155 – 165 million pounds. In 2019, lower mined grades (estimated annual run-of-mine of 14.0% in 2019 versus 14.9% in 2018) will lead to reduced metal production and consequently slightly higher operating costs.
The new high-efficiency heavy fuel oil power plant is nearing completion. We expect cost savings of approximately $5 per tonne to be realized once it is fully operational. The reduction in power costs, however, is expected to be mostly offset by reduced production levels, resulting in similar costs per tonne as seen over recent quarters.
Record concentrate trucking during December lowered site inventories to 24 kilotonnes at year end, significantly below historic and anticipated inventory staging levels ranging from 30 – 35 kilotonnes. The Company continues to focus on logistic improvements and initiatives to minimize concentrate levels as far as feasible.
| Table 2: Perkoa Preliminary Q4-2018 Production (100 percent basis) | ||||
| Three months ended December 31 |
Twelve months ended December 31 |
|||
| 2018 | 2017 | 2018 | 2017(1) | |
| Tonnes mined | 161,815 | 203,635 | 708,263 | 270,909 |
| Tonnes milled | 185,661 | 180,022 | 724,995 | 237,832 |
| Payable production: Zinc (million pounds) Zinc (tonnes) |
47.6 21,577 |
47.7 21,627 |
183.9 83,428 |
62.8 28,483 |
(1) Twelve months ending December 31, 2017 consolidated preliminary production includes only September 1 to December 31, 2017. Trevali acquired the Perkoa mine on August 31, 2017.
(2) Please refer to “Use of Non-IFRS Financial Performance Measures” below.
Rosh Pinah Mine, Namibia
Similar to the third quarter of 2018, harder ore and head grades above mill design from the new Western Ore Field resulted in lower throughput and recovery. Ongoing projects, such as a new filter press, as well as flotation circuit and grinding circuit modifications are budgeted to resolve these issues in 2019 and are being appropriately sized to facilitate any potential future throughput increases. The increase in capital expenditures planned for 2019 reflect these enhancements and are being incorporated into the Rosh Pinah 2.0 study, which is evaluating an increase in mill throughput by 50% and is advancing to P/BFS level study with final results anticipated in H2 2019.
| Table 3: Rosh Pinah Preliminary Q4-2018 Production | ||||
| Three months ended December 31 |
Twelve months ended December 31 |
|||
| 2018 | 2017 | 2018 | 2017(1) | |
| Tonnes mined | 158,354 | 177,820 | 627,295 | 237,865 |
| Tonnes milled | 149,201 | 171,020 | 641,980 | 227,650 |
| Payable production: Zinc (million pounds) Zinc (tonnes) Lead (million pounds) Lead (tonnes) Silver (thousand ounces) |
25.4 11,675 1.5 677 22 |
21.3 9,681 3.1 1,398 49 |
94.2 42,706 8.5 3,870 104 |
29.3 13,299 4.4 1,986 68,533 |
(1) Twelve months ending December 31, 2017 consolidated preliminary production includes only September 1 to December 31, 2017. Trevali acquired the Rosh Pinah mine on August 31, 2017.
(2) Please refer to “Use of Non-IFRS Financial Performance Measures” below.
Caribou Mine, Canada
Planned remediation works (increased development, ground support and installation of cemented fill in key areas of the mine) remain on track to return the mine to normal production levels in Q2 2019 but will result in higher operating costs particularly in Q1. The technical team continues to evaluate modifications to the extraction method in order to improve productivity and decrease costs, in addition to ongoing short- and long-term strategic reviews of the Bathurst Mining Camp.
| Table 4: Caribou Preliminary Q4-2018 Production | ||||
| Three months ended December 31 |
Twelve months ended December 31 |
|||
| 2018 | 2017 | 2018 | 2017 | |
| Tonnes mined | 184,635 | 250,225 | 887,141 | 937,459 |
| Tonnes milled | 174,180 | 252,857 | 884,529 | 945,436 |
| Payable production: Zinc (million pounds) Zinc (tonnes) Lead (million pounds) Lead (tonnes) Silver (thousand ounces) |
13.7 6,214 5.5 2,485 122 |
21.7 9,826 8.7 3,941 250 |
72.0 32,639 25.3 11,456 632 |
79.9 36,264 30.9 14,026 890 |
(1) Please refer to “Use of Non-IFRS Financial Performance Measures” below.
Santander Mine, Peru
Over the course of the fourth quarter, Santander transitioned to fully owner operated, recovered from third quarter production disruptions and met its forecasted annual production target, delivering a 2018 monthly zinc production record in December. The mine is well positioned for production in 2019 with all development in place for the year.
| Table 5: Santander Preliminary Q4-2018 Production | ||||
| Three months ended December 31 |
Twelve months ended December 31 |
|||
| 2018 | 2017 | 2018 | 2017 | |
| Tonnes mined | 218,580 | 201,198 | 750,970 | 681,785 |
| Tonnes milled | 228,454 | 214,791 | 803,265 | 839,546 |
| Payable production: Zinc (million pounds) Zinc (tonnes) Lead (million pounds) Lead (tonnes) Silver (thousand ounces) |
16.0 7,236 2.7 1,244 142 |
14.1 6,396 1.7 764 98 |
56.8 25,760 7.9 3,588 435 |
53.1 24,076 10.5 4,779 603 |
(1) Please refer to “Use of Non-IFRS Financial Performance Measures” below.
2019 CONSOLIDATED PRODUCTION GUIDANCE
Consolidated production guidance for 2019 is estimated between 361 – 401 million pounds of payable zinc, 44 – 49 million pounds of payable lead and 1.3 – 1.5 million ounces of payable silver.
| Table 6: 2019 Consolidated Production Guidance (1&2) | |||
| Mine | 2019 Zinc Production | 2019 Lead Production | 2019 Silver Production |
| Perkoa (100%) | 151 – 168 million lbs 68 – 76 ktonnes |
N/A | N/A |
| Rosh Pinah (100%) | 80 – 89 million lbs 36 – 40 ktonnes |
10 – 11 million lbs 4 – 5 ktonnes |
145 – 161 k ozs |
| Caribou | 71 – 79 million lbs 32 – 36 ktonnes |
24 – 27 million lbs 11 – 12 ktonnes |
641 – 713 k ozs |
| Santander | 59 – 65 million lbs 27 – 29 ktonnes |
10 – 11 million lbs 4 – 5 ktonnes |
536 – 595 k ozs |
| Total | 361 – 401 million lbs 163 – 181 ktonnes |
44 – 49 million lbs 19 – 22 ktonnes |
1,322 – 1,469 k ozs |
(1) Constitutes forward-looking information; see “Cautionary Note Regarding Forward-Looking Statements”.
(2) Trevali’s ownership interest is 90% of Perkoa and 90% of Rosh Pinah.
Consolidated operating costs are forecast to range from $69 – $76 per tonne, with cash costs (net of by-product credits) of between $0.81 – $0.88 per pound of zinc (see Table 7). Including capital expenditures forecast of $74 million, consolidated AISC are expected to range from $0.99 – $1.09 per pound of zinc (for the purpose of AISC guidance, all capital is considered to be sustaining). Relative to 2018, higher capital expenditures at Rosh Pinah and Santander are planned, with incremental spending on process plant upgrades (new filter press and floatation and grinding circuit improvements) and power infrastructure, respectively, the main drivers.
| Table 7: 2019 Consolidated Operating Cost and Capital Expenditure Guidance (1&2) | ||||
| Mine | Operating Costs (per tonne) |
Cash Costs net of By-product Credits ($/lb Zn) |
All-in Sustaining Costs ($/lb Zn) |
Capital Expenditures ($M) |
| Perkoa (100%) | 106 – 117 | 0.84 – 0.92 | 0.91 – 0.99 | 11 |
| Rosh Pinah (100%) | 56 – 63 | 0.70 – 0.77 | 0.99 – 1.09 | 26 |
| Caribou | 72 – 79 | 0.95 – 1.02 | 1.15 – 1.28 | 16 |
| Santander | 45 – 49 | 0.71 – 0.78 | 1.02 – 1.13 | 21 |
| Exploration | – | – | – | 8 |
| Total | 69 – 76 | 0.81 – 0.88 | 0.99 – 1.09 | 82 |
(1) Constitutes forward-looking information; see “Cautionary Note Regarding Forward-Looking Statements”.
(2) Trevali’s ownership interest is 90% of Perkoa and 90% of Rosh Pinah.
Quarterly Variability
Zinc: While production guidance has been provided on an annual basis, we expect moderate production fluctuations on a quarter-to-quarter basis due to mine scheduling. Zinc production overall is forecast to be slightly stronger in the second half of 2019, with Caribou in particular expected to deliver a weaker quarter in Q1 as the Company completes the advanced rates of development and production catches up in Q2 – Q4. Conversely, Rosh Pinah is forecast to have a stronger start to 2019, with production strongest in Q1 and declining thereafter as zinc grades decline from approximately 10% to 8%. Due to the mining sequence, lower grades are planned at Perkoa in Q2 and Q3.
Lead: Production is expected to show more quarterly variability than zinc, with consolidated lead production increasing in each successive quarter throughout 2019. Lead grades at Santander and Rosh Pinah are forecast to increase throughout the year, with Rosh Pinah expected to mine significantly higher lead grades in the second half of 2019.
Operating costs: The Company expects costs to generally be at their highest level for each mine in Q1 with consolidated costs per tonne to range from $73 – $81 per tonne during the quarter. Operating costs will be higher in Q1 compared to the yearly target due to the following:
Exploration – Targeting Resource and Reserve Growth and Mine Life Extensions
The exploration group is on track to successfully replace mined inventory at all the operations in addition to modestly increasing resources. Specific highlights include the emerging Santander Pipe deposit, which will remain a focus for 2019 and material extensions to the Perkoa deposit where the Hanging Wall zone was extended approximately 300 meters below the current mine plan. Finally, regional exploration drilling commenced at Perkoa in Q4 and to date has successfully intersected sulphide bearing (stringer – disseminated to narrow massive zones – non-economic to date) VMS systems at several of the targets. Drill testing is ongoing.
The 2019 exploration program will continue to focus on brownfield, near-mine, exploration targets to expand and discover new resources in proximity to existing mine infrastructure and extend the current mine lives. For 2019, the Company intends to invest a minimum $8.4 million on approximately 36,300 metres of diamond drilling from surface and underground primarily focused on the Perkoa and Santander mineral systems. Contingent on positive results and available funds, additional funding may be deployed towards further drilling.
Updated resource and reserve estimates at all sites are expected to be completed at the end of the first quarter of 2019.
Qualified Person and Quality Control/Quality Assurance
EurGeol Dr. Mark D. Cruise, Trevali’s President and CEO, is a qualified person as defined by NI 43-101, has supervised the preparation of, and has verified the scientific and technical information that forms the basis for this news release. Dr. Cruise is not independent of the Company as he is an officer, director and shareholder.
ABOUT TREVALI MINING CORPORATION
Trevali is a zinc-focused, base metals company with four mines: the 90% owned Perkoa mine in Burkina Faso, the 90% owned Rosh Pinah mine in Namibia, the wholly-owned Caribou mine in the Bathurst Mining Camp of northern New Brunswick in Canada, and the wholly-owned Santander mine in Peru.
The shares of Trevali are listed on the TSX (symbol TV), the OTCQX (symbol TREVF), the Lima Stock Exchange (symbol TV), and the Frankfurt Exchange (symbol 4TI). For further details on Trevali, readers are referred to the Company’s website (www.trevali.com) and to Canadian regulatory filings on SEDAR at www.sedar.com.
On Behalf of the Board of Directors of
TREVALI MINING CORPORATION
“Mark D. Cruise” (signed)
Mark D. Cruise, President
Contact Information:
Steve Stakiw, Vice President – Investor Relations and Corporate Communications
Email: sstakiw@trevali.com
Phone: (604) 488-1661 / Direct: (604) 638-5623
IBF4
![]()