Follow Us! Like Our Page!

‘They beat us into submission’: West Moberly’s decades-long fight against Site C dam is over – The Narwhal

June 28, 2022

West Moberly First Nations reluctantly signed a settlement seven years into construction on the beleaguered hydroelectric project on the Peace River in northeastern B.C.

After a decades-long fight against the Site C dam, Monday was a bittersweet day for West Moberly First Nations Chief Roland Willson.

The Nation and the province announced a partial settlement agreement has been reached over the beleaguered hydroelectric project on the Peace River in northeastern B.C., which will see the release of West Moberly’s claims against the Site C project in exchange for an impact and benefits agreement and contracting opportunities.

Read More: https://thenarwhal.ca/site-c-dam-settlement/

 80 total views,  2 views today