Press Release
August 17, 2023
The Honourable Bernard Davis, Minister of Environment and Climate Change, has announced the following relative to Part 10 Environmental Assessment of the Environmental Protection Act.
UNDERTAKING REGISTERED:
Valentine Gold Project Expansion – Berry Pit (Reg. 2262)
Proponent: Marathon Gold Corporation
The Proponent is proposing an expansion to the gold mine project at Valentine Lake located approximately 55 kilometres southwest of Millertown in central Newfoundland.
The proposed expansion is to develop a third open pit within the mine site of the Valentine Gold Project. Development would include haul roads, stockpiles for waste rock/topsoil, expansion of low-grade ore/overburden stockpiles, and additional water management infrastructure. A description of the project can be found on the department’s webpage at: www.gov.nl.ca/eccm/env-assessment/projects-list/.
The undertaking was registered on August 17, 2023; the deadline for public comment is September 21, 2023; and the minister’s decision is due by October 1, 2023.
ENVIRONMENTAL ASSESSMENT COMMITTEE APPOINTED:
Badger Sand and Gravel Quarry (Reg. 2247)
Proponent: Exploits Welding and Machine Shop Limited
An Environmental Assessment Committee (EAC) has been appointed to provide scientific and technical advice to the minister and to prepare guidelines to advise the proponent of the information to be included in an environmental preview report. The EAC includes representation from the following government departments:
UNDERTAKINGS RELEASED:
Salvage Microbrewery (Reg. 2253)
Proponent: Wild Cove Adventures Limited.
The project is released from environmental assessment subject to the following conditions:
Freshwater Kennedy Farm Abattoir (Reg. 2254)
Proponent: Kennedy Farm Inc.
The project is released from environmental assessment subject to the following conditions:
Learn more
Environmental Assessment Division
Department of Environment and Climate Change
West Block, Confederation Building
P.O. Box 8700, St. John’s, NL A1B 4J6
Environmental assessment information is available at:
www.gov.nl.ca/ecc/env-assessment/
www.gov.nl.ca/ecc/files/GUIDE-TO-THE-PROCESS_May-2023.pdf
Follow us on Twitter: @GovNL and @ECC_GovNL
Public comments may be forwarded to: EAprojectcomments@gov.nl.ca
If you submit comments on a project that is under environmental assessment, please advise the Department if you DO NOT wish to share your comments with the project proponent.
IBF4
![]()