Press Release
Overall Construction Reached 72%, Reflecting Strong and Efficient Execution
Project Remains on Schedule for Mid 2026 Commercial Production and On Budget
Vancouver, BC (November 17, 2025) – Foran Mining Corporation (TSX: FOM) (OTCQX: FMCXF) (“Foran” or the “Company”) is pleased to report on construction activities completed during the month of October 2025 at its 100% owned McIlvenna Bay project in Saskatchewan. With the project now approximately 72% complete, McIlvenna Bay remains on schedule for commercial production in mid-2026 and continues to track on budget.
Key Achievements from the month of October 2025:
Dan Myerson, Executive Chairman and CEO of Foran, commented “Reaching 72% completion is a very meaningful milestone for our team and speaks to the steady progress underway across the entire project. Month after month, we are delivering on our development objectives, advancing major surface and underground infrastructure and building real momentum as we move toward first production next year. What we are seeing on site today is the result of many decades of hard and meticulous work, and a clear plan that is being executed with discipline, and every milestone achieved brings us closer to introducing a new copper, zinc, gold and silver asset at a pivotal moment for global metals supply. As we enter the final phases of construction, our sole focus remains on driving high quality and safe execution, while thereby positioning the mine to create lasting value for our communities, our shareholders and Canada.”
Construction Progress Summary
| Description | Progress to Date (as of October 31, 2025, unless otherwise stated) |
| Health & Safety | Site wide lost time incident frequency rate (“LTIFR”) year-to-date of 0.7 and a total recordable incident frequency rate (“TRIFR”) year-to-date of 2.6 after over 1,790,000 total person-hours worked year-to-date. |
| Construction Progress & Schedule | Overall project construction progress was approximately 72% at month-end, performing in line with monthly targets. The project continues to remain within the revised capital estimate disclosed in the May 13, 2025 press release. Commercial production target reiterated for mid 2026. |
| Surface Development (Plant) | Civil works were completed in several key areas in October including the crusher electrical room, grinding electrical room, primary crusher, secondary grinding area, and copper and zinc concentrate areas. Structural steel installation remains on track. Installation of surface ore conveyor towers continued. Erection of materials storage tanks and structural steel for the ore bin progressed. HVAC installation continued throughout the process plant and truck shop. Transmission line construction is advancing well, with installation of tower structures ongoing, and with conductor stringing scheduled to commence in early November. Progress on the main electrical substation at site has advanced well, with completion tracking on schedule for the end of December 2025, with line energization remaining on schedule for March 2026. Electrical installation achieved significant progress across multiple areas including the process plant, tailings storage facility return water line, and copper and zinc concentrate systems. |
| Underground Development | Development included approximately 568m of lateral advance, with 56m of decline development, with the ramp now extending approximately 6m past the 240m level. Slashing of the fresh air raise was completed, with the installation of final ground support initiated. Production drilling continued in October on the 150m and 180m levels. Undercut slash drilling was completed in three stopes. Completed development of the 120 ramp BEV truck charge station. Completed development of the 150m level explosives storage. Added approximately 13,000 tonnes to the surface ore stockpile in October, bringing the total to approximately 138,000 tonnes at month end, supporting mill commissioning readiness. |
| Human Resources | Approximately 803 persons on site, with 164 Foran employees and 639 construction personnel. |
Site Layout – Looking South
Process Plant – Looking North
Process Plant and Crushed Ore Conveyor Assembly and Ore Bin
Mine Laydown, Maintenance Shop, and Warehouse Area
Primary Crusher
Process Plant with Underground Mine Portal
Process Plant Electrical Installations
Surface Fresh Air Raise Fan Infrastructure
Mechanized Bolter Installing Ground Support
Qualified Person
Mr. Samuele Renelli, P. Eng., Vice President, Technical Services for Foran, is the Qualified Person for all technical information in this news release and has reviewed, verified and approved the technical information in this news release.
FOR ADDITIONAL INFORMATION & MEDIA ENQUIRIES:
Jonathan French, CFA
VP, Capital Markets & External Affairs
409 Granville Street, Suite 904
Vancouver, BC, Canada, V6C 1T2
ir@foranmining.com
+1 (604) 488-0008
IBF4
![]()