Press Release
Vancouver, BC (March 26, 2026) – Foran Mining Corporation (TSX: FOM) (OTCQX: FMCXF) (“Foran” or the “Company”) is pleased to provide a construction update for the month ending February 28, 2026 at its 100% owned McIlvenna Bay project in Saskatchewan, Canada. Project completion stands at approximately 91%, remains on schedule for commercial production in mid-2026 and proceeding within budget.
Key Achievements as at February 28, 2026 (unless otherwise stated):
Dan Myerson, Executive Chairman and CEO of Foran, commented “February marked a pivotal milestone for Foran, with McIlvenna Bay surpassing 90% completion and entering cold commissioning on schedule. We are now in the final stages of operational readiness as we prepare to introduce first ore to the mill, a milestone strategically timed with the recent energization of our renewable hydropower line. These achievements are a direct result of our greatest competitive advantage: our people. Their relentless drive, commitment to safety, and unified focus have de-risked our path toward bringing Canada’s next premier copper mine into production. We are building a long-term legacy that will provide the critical minerals required for the global energy transition, and we look forward to sharing further updates as we transition into hot commissioning and scale toward commercial production by mid-2026.”
Construction Progress Summary
| Description | Progress to Date (as of February 28, 2026, unless otherwise stated) |
| Health & Safety | Site wide lost time incident frequency rate (“LTIFR”) year-to-date of 0.4 and a total recordable incident frequency rate (“TRIFR”) year-to-date of 2.1 after over 558,000 total person-hours worked year-to-date. |
| Construction Progress & Schedule | Overall project construction progress stood at approximately 91%. Commercial production remains in line with previous guidance, anticipated by mid-2026. The project is proceeding within the revised capital estimate disclosed in Foran’s May 13, 2025 press release. Subsequent to quarter end, the 85 km, 110 kV transmission line was energized, marking a major infrastructure milestone by connecting McIlvenna Bay to renewable hydroelectric power ahead of schedule and on budget. |
| Surface Construction (Plant) | Completed remaining civil works scope in the tailings handling and paste backfill areas. Completed installations of overland conveyors and belts. Continued progress at paste plant with mechanical, piping and electrical installations. Completed thickener tank installations and pump house building. Continued progress within reagents infrastructure, including structure installation, skid assembly and mechanical, piping and electrical installations. Mechanical and piping installations remain in-line with schedule, and during the month, completed installations in the grinding and classification areas in the plant. Installation of HVAC nearing completion in the process plant and concentrate handling areas. Electrical installation completed in the mine electrical room and instrumentation installation completed across various areas of the process plant. Fire detection system inspection completed in the crusher, grinding and tailings area electrical rooms, as well as for the emergency generators. |
| Commissioning Activities | Completed idle run of the ball mill. Pre-commissioning started on thickener. Mechanical commissioning continued on grinding electrical rooms, SAG and ball mills, and copper flotation circuit motor runs and input and output testing. Deployment of instrument air. 110m level battery electric vehicle charging bay commissioning continued in February. |
| Underground Development | Development included approximately 505m of lateral advance, with approximately 70m of decline development, with the decline now extending approximately 34m past the 270m level. Underground drilled and/or blasted inventory stood at approximately 220,000 tonnes at the end of February. Added approximately 35,000 tonnes to the surface ore stockpile in February, bringing the total to approximately 271,000 tonnes at month end. |
| Human Resources | Total contractor and employee workforce was approximately 800 people on site at month-end. |
Process Plant Interior
Crushed Ore Bin and Conveyance Systems
Qualified Person
Mr. Samuele Renelli, P. Eng., Vice President, Technical Services for Foran, is the Qualified Person for all technical information in this news release and has reviewed, verified and approved the technical information in this news release.
FOR ADDITIONAL INFORMATION & MEDIA ENQUIRIES:
| Foran: |
| Jonathan French, CFA |
| VP, Capital Markets & External Affairs |
| 409 Granville Street, Suite 904 |
| Vancouver, BC, Canada, V6C 1T2 |
| ir@foranmining.com |
| +1 (604) 488-0008 |
IBF4
![]()