VANCOUVER, B.C., January 26, 2026: Gold X2 Mining Inc. (TSXV: AUXX / OTCQB: GSHRF / FRA: DF8 ) (“Gold X2” or the “Company”) is pleased to announce the results of its Preliminary Economic Assessment1 (the “PEA”) and updated Mineral Resource Estimate2 (“MRE”) for its 100% owned Moss Gold Project in Ontario, Canada (the “Moss Gold Project”, “Moss” or the “Project”).
Summary of PEA Results3
PEA and MRE Summary
Gold X2 retained G Mining Services (“G Mining” or “GMS”) to complete the PEA and prepare a technical report in in compliance with the guidelines of National Instrument 43-101 Standards of Disclosure for Mineral Projects (“NI 43-101“).
The PEA is derived using the Company’s MRE effective as at January 16, 2026. The effective date of the PEA is January 26, 2026, and a NI 43-101 compliant technical report (the “Technical Report“) will be filed on the Company’s website and under its SEDAR+ profile within 45 days of this news release.
Michael Henrichsen, CEO of Gold X2 commented: “The Moss deposit MRE and PEA represents a major milestone for the Company as we have clearly demonstrated the potential for the Moss Deposit to be a top ten gold producer in Canada1,2. The Project benefits from exceptional infrastructure with the Trans-Canada highway and high-voltage powerlines within 12 kms of the proposed mine site. The PEA has outlined robust economics at a gold price of US$2,750, representing a base case scenario that the Company believes can be improved through potential resource expansion immediately adjacent to the design pit, enhanced metallurgical recoveries, and optimization of the mine schedule.
The Company has done extensive work internally and with G Mining to ensure a realistic high-quality study underpinned by solid geological and engineering work. We look forward to advancing the Project towards a Feasibility Study and the formal permitting process in the second half of 2027.”
PEA Summary
Property Description, Location and Access
Gold X2 Mining’s Moss Gold Project is located approximately 110km west of Thunder Bay, the largest population centre in Northern Ontario with a population of over 110,000. Moss benefits from well-established infrastructure, including: (1) Trans-Canada highway connectivity to city of Thunder Bay; (2) low-cost high-voltage hydroelectric power line capacity within 12km of the Project; (3) deep-water port access in Thunder Bay; and (4) railway access.
The PEA is based on a conventional open pit mining and milling-flotation-leach operation with a nameplate processing capacity of 30,000 tonnes per day. The study illustrates average annual payable gold production of approximately 265,000 ounces and 374,000 ounces of silver, respectively, over an initial 13.2 year mine life. Table 1 presents the key operating and financial highlights from the PEA, using the base case assumptions of US$2,750/oz gold, long term consensus gold price forecast of US$3,137/oz, and spot gold prices of US$4,600/oz.
Table 1: Operating and Financial Summary6
Updated Mineral Resource Estimate
Figure 1: Moss Deposit and East Coldstream Deposit MRE (January 2026)
Notes to the Mineral Resource statement:
The MRE has focused on the open pit mineralization at the main deposits, being the Moss Deposit and the East Coldstream Deposit, and excludes any underground resources, as well as the Span Lake satellite deposit.
Structural domain modelling and grade interpolation utilises 357 historical diamond drill holes (105,445m) and 210 Gold X2 diamond drill holes (94,094m) at Moss, and 132 historical diamond drill holes (29,841m) and 15 Gold X2 diamond drill holes (7,479m) at East Coldstream Deposit. Both models use a parent block size of 5 x 5 x 5m – the selective mining unit (SMU) – to focus the construction of the resource on mineable block sizes. This is sub-celled to 1.25 x 1.25 x 1.25m to improve volumetric precision.
Both models are based on an updated, robust structural model that utilises oriented drill core measurements from Gold X2’s drilling. Along with increased drill density at Moss, this has resulted in improved grade continuity and geostatistical metrics that have resulted in a 73% increase in the ounces reported in the Indicated category.
Resource categories uses an average 3DDH isotropic search of <45 meters for Indicated, which is manually edited to remove isolated pods, and an average 3DDH isotropic search of <90 meters for Inferred.
The Moss Deposit has sufficient silver mineralization for an estimate of silver to be included in the MRE. Silver concentrations are lower at East Coldstream and have not been modelled.
The PEA is based exclusively on the Mineral Resource defined at the Moss Deposit. The resource model has been regularised to the 5 x 5 x 5m SMU and a 1m dilution skin to contact blocks to account for mining dilution.
The PEA is preliminary in nature and includes Inferred Mineral Resources. Inferred Mineral Resources are considered too speculative geologically to have the economic considerations applied to them that would enable them to be categorized as mineral reserves, and there is no certainty that the PEA will be realized.
Production Profile
The PEA outlines an average annual production profile of approximately 265,000 ounces of gold and 374,000 ounces of silver respectively over an initial 13.2 year mine life. Total gold production is estimated to be 3.6 million ounces with an average milled grade of 0.88 g/t Au, and a total of 4.5 million ounces of silver at an average milled grade of 1.37 g/t Ag.
Figure 2: Illustrates the Gold Equivalent ounce production profile over the LOM based on payable Gold and Silver calculated using US$2,750/oz Au and US$35.00/oz Ag.
Mining
The mine plan is based on conventional open pit truck-and-shovel methods with a mill processing capacity of approximately 30,000 tpd over the 13.2 LOM. The pit optimization study used a gold price of US$2,000/oz. The optimal pit shell was selected on the basis of maximum NPV and corresponded to a revenue factor of 0.81. This pit shell contains approximately 138,982 kt of mill feed at 0.88 g/t, 668,255 kt of waste, and 72,208 kt of overburden resulting in a strip ratio of 5.3:1. The open pit operation is planned to be executed over 3 phases, including 20 months of pre-production mining and 6 months of ramp up processing, with an owner operated mining fleet.
Processing and Recovery
The PEA envisions a 30,000 tonne-per-day processing facility based on a standard metallurgical flowsheet, consisting of grinding to p80=55 microns, rougher flotation, regrind of concentrate to p80=15 microns, carbon-in-leach (CIL) of flotation tailings and concentrate, and adsorption to produce gold doré. CIL tailings will be treated in a cyanide destruction circuit and pumped to a traditional tailings storage facility. Metallurgical testing indicates clean, non-refractory gold mineralization with an average gold recovery of 91.7% for gold and 82.8% for silver for the PEA. Figure 3 illustrates the processing flow sheet for the Moss Deposit.
Figure 3: Moss Deposit Processing Flowsheet
Power
The process plant is contemplated to utilize 40 megawatts of power that can be supplied via a 12km power spur from the main Hydro One power line along Highway 11. Hydro One with its indigenous partners is currently installing the Waasigan power line that will add 350 megawatts capacity to the power corridor. Expected power costs are 11 cents/kilowatt hour based on discussions with Hydro One and a review of the Ontario power tariffs.
Operating Costs
LOM operating costs are estimated at US$999 per ounce of gold produced, excluding royalty costs, as summarized below. The LOM AISC is estimated to be US$1,188 per ounce of gold produced based with operating costs anticipated to average C$34.44/tonne processed as outlined in Table 2 below. The cost structure places the Project in the second quartile of the global gold cost curve7.
Table 2 – Summary of Operating and Capital Costs8
Project Royalties
Only mineralized blocks on the fringe of the deposit are subject to a net smelter returns (“NSR”) royalty that is equivalent to an average LOM NSR of 0.11% across the deposit. There is a Net Profit Interest of 7.25% on the Moss Deposit that is payable after costs associated with acquisition, exploration, development, initial and sustaining capex, operating expenses, royalties, taxes, and corporate overheads not exceeding 5% of sales are deducted.
Capital Cost Estimates
The initial capital cost (“capex”) is estimated to be $2.001 billion and excludes working capital. An 18% contingency of $303 million is included in the estimate. The total construction period, including the early earthworks program, is forecast to be 30 months. The project is anticipated to have a ramp up during the last 6 months of the construction period and is anticipated to generate revenue prior to commercial production.
Figure 4: Illustrates the initial CAPEX and sustaining cost breakdown
The sustaining capex is estimated to be $839 million earmarked for additional equipment, replacement units, and major repairs. Other sustaining capex captures tailings storage facility, power line and surface infrastructure costs. Working capital during construction is budgeted at $39 million and closure and monitoring costs at $49 million.
The PEA provides an after-tax NPV5% of $2.232 billion, an IRR of 22.1% and a payback period of 3.2 years from first production at a gold price of $2,750/oz and an exchange rate $1.34 USD/CAD. Table 3 presents the sensitivity analysis after-tax NPV5%, IRR, payback period and cumulative Free Cash Flow to changes in gold price. It should be noted that sensitivities apply to the financial model only; pit selection, cut-off grade and processing schedules are based on a US$2,000 gold price and would likely be redesigned to optimize for significantly higher or significantly lower fold price scenarios.
Table 3 – Base Case Sensitivity to Gold Price (Other Constant Assumptions Ag: US$35.00/oz, USD/CAD $1.34)
Environmental and Permitting
Gold X2 has, through CSL Environmental & Geotechnical, conducted existing conditions environmental studies since mid-2021. In parallel, with the support of One-Eighty Consulting Group, Gold X2 has carried out early engagement with potentially affected Indigenous Nations. Since the start of 2025, this work has expanded in scope and scale and will support future engineering studies and collaborative efforts to manage potential environmental effects.
This ongoing work will also form the basis of a future environmental assessment (“EA”) and relevant permitting processes. The Company has commenced, well ahead of entering these processes, a process to engage an experienced environmental consultant to evaluate the existing conditions studies and to support the EA for the Project. Based on available information and ongoing work, the Project is well positioned to advance toward the next stage of development.
Opportunities and Exploration Potential
The PEA presented represents a robust evaluation of a mining scenario at the Moss Deposit and will allow the Company to proceed directly to a Feasibility Study. While care has been taken to provide accurate estimates and realistic assumptions, additional analysis and collection of data will provide opportunities for further refinements of the proposed mining operation that could potentially improve the technical and financial performance of the deposit.
Resource Expansion and Exploration Potential
There is potential both within and adjacent to the RPEEE pit to convert unclassified mineralization with increased drill density that has the potential to increase the size of the deposit, the annual production profile and mine life.
In addition, the Moss Deposit remains open at depth with potential to delineate higher grade mineralization associated structural controls that could support a larger pit and/or underground mining scenario. Exploration drilling at depth is on-going with results expected in the coming months. Along strike, the deposit is open to the SW across a NNE trending fault that has offset the Moss Deposit to the south-southwest. This trend has been defined over approximately 10 km of strike length, across the claims recently acquired from Kesselrun Resources, and will be a focus of the Company’s exploration plans in 2026 and 2027. In addition, gold mineralization has been defined over 5km along the Deaty trend, a parallel structure, located approximately 3km to the south of the Moss Deposit. Initial drill results from the first drill fence across the structure are anticipated within the coming months. The Company plans to continue drilling along this prospective structural corridor in 2026.
The Company has completed its grade control drilling programs at the Main and QES Zones. Results are expected in the coming months and will be used to reconcile the MRE against the closed paced drilling data. This will approximate a mining scale review of the model that the Company anticipates will significantly de-risk the project.
In addition to infill drilling to convert Inferred to Indicated Mineral Resources, the Company is planning geotechnical drilling around the proposed pit margin to assess the stability of wall rocks, which may lead to steeper pit slopes that would in turn reduce the stripping ratio. Sample from the grade control drilling will provide composites for Feasibility-scale metallurgical test work to optimise the current process flowsheet, including the potential inclusion of an ore sorting process for lower grade mineralization and a gravity recovery circuit.
Finally, the current mine schedule does not include any stockpile management, which has been proven in earlier scoping reviews to increase the grade of mill feed and annual gold production in the first five years of production. Additional engineering studies to assess steeper slopes and stockpile management will be conducted during 2026 as the supporting data is collected.
Project Timeline and Next Steps
Figure 5: Illustrates 2-year project schedule to enter FS, EA and Permitting
Qualified Assurance Program and Quality Control Measures (“QA/QC”)
In this Mineral Resource Estimate both historical and modern assays were included. Quality assurance and quality control (“QA/QC”) procedures were applied to modern drilling programs. QA/QC protocols included the systematic insertion of certified reference materials, blanks, and field duplicates into the sample stream at regular intervals. Samples from the modern drilling programs were prepared and analyzed by ALS Laboratories in Thunder Bay, ON, an independent and accredited laboratory, using industry-standard sample preparation procedures and fire assay methods with atomic absorption (Au-AA23) for gold and four acid digestion followed by ICP-MS measurement (ME-MS61) for silver. Samples assaying >10.0 g/t Au are re-analyzed with a gravimetric finish. QA/QC results were reviewed by the Qualified Person and are considered acceptable, with no material issues identified that would affect the reliability of the assay data.
Historical assays have been validated through extensive validation procedures and analyses. Re-assaying of historic drilling is ongoing with re-assayed values included in the resource estimate.
The Qualified Person is of the opinion that the historical and modern assay database is of sufficient quality to support Mineral Resource Estimate (MRE) and the PEA.
Technical Report Preparation and Qualified Persons
The PEA has an effective date of January 26th, 2026 and was issued on January 26th, 2026. It was authored by independent Qualified Persons and is in accordance with National Instrument 43-101 – Standards of Disclosure for Mineral Projects.
GMS was responsible for the overall report and PEA coordination, property description and location, accessibility, history, mineral processing and metallurgical testing, mineral resource estimation, mining methods, recovery methods, project infrastructures, operating costs, capex, economic analysis and project execution plan. For readers to fully understand the information in this news release, they should read the technical report in its entirety following publication, including all qualifications, assumptions, exclusions and risks. The technical report is intended to be read as a whole and sections should not be read or relied upon out of context.
The technical content of this press release has been reviewed and approved by the independent QPs who were involved with preparation of the PEA:
Use of Non-GAAP Measures
Certain financial measures referred to in this news release are not measures recognized under International Financial Reporting Standards (“IFRS”) and are referred to as non-GAAP financial measures or ratios. These measures have no standardized meaning under IFRS and may not be comparable to similar measures presented by other companies. The definitions established and calculations performed by Gold X2 are based on management’s reasonable judgement and are consistently applied. These measures are intended to provide additional information and should not be considered in isolation or as a substitute for measures prepared in accordance with IFRS.
The non-GAAP financial measures used in this news release and common to the gold mining industry are all-in sustaining cost per ounce of gold sold, and free cash flow. All-in sustaining cost per ounce of gold sold and free cash flow are non-GAAP financial measures or ratios and have no standardized meaning under IFRS and may not be comparable to similar measures used by other issuers. As the Moss Gold Project is not in production, the Company does not have historical non-GAAP financial measures nor historical comparable measures under IFRS, and therefore the foregoing prospective non-GAAP financial measures or ratios may not be reconciled to the nearest comparable measures under IFRS.
About Gold X2
Gold X2 is a growth-oriented gold company focused on delivering long-term shareholder and stakeholder value through the acquisition and advancement of primary gold assets in tier-one jurisdictions. It is led by the ex-global head of structural geology for the world’s largest gold company and backed by one of Canada’s pre-eminent private equity firms. The Company’s current focus is the advanced stage 100% owned Moss Gold Project which is positioned in Ontario, Canada, with direct access from the Trans-Canada Highway, hydroelectric power near site, supportive local communities and skilled workforce. The Company has invested over $100 million of new capital and completed approximately 100,000 meters of drilling on the Moss Gold Project, which, in aggregate, has had over 300,000 meters of drilling. The 2026 updated NI 43-101 mineral resource estimate (“MRE”) for the Moss and East Coldstream Deposits has expanded to 2.458 million ounces of Indicated gold resources at 1.04 g/t Au, contained within 73.8 million tonnes and 4.209 million ounces of Inferred gold resources at 0.97 g/t Au contained within 134.7 million tonnes. The Moss Deposit also has a silver MRE of 3.160 million ounces of indicated silver resources at 1.53 g/t Ag contained within 64.3 Mt and 6.273 million ounces of inferred silver resources at 1.55 g/t Ag contained within 125.9 Mt. Results of a preliminary economic assessment (“PEA”) of the Moss Gold Project suggest the potential for the deposit to support a long-life mining operation with a strong production profile and low production costs. The MRE and PEA are supported by a NI 43-101 technical report for the Moss Gold Project which will be filed on SEDAR+ (www.sedarplus.ca) and the Company’s website by March 12, 2026. For more information, please visit SEDAR+ (www.sedarplus.ca) and the Company’s website (www.goldx2.com).
For More Information – Please Contact:
Michael Henrichsen
President, Chief Executive Officer and Director
Gold X2 Mining Inc.
E: mhenrichsen@goldx2.com
W: www.goldx2.com
T: 1-604-404-4335
IBF5
![]()