VICTORIA – The Ministry of Energy and Mines (MEM) and the Ministry of Environment (MOE) have implemented a plan to ensure Bralorne Gold Mine (BGM) near Lillooet, B.C. is in compliance with its permit conditions after heavy rainfall this past weekend.
To support this plan, the chief inspector of mines has ordered BGM to complete the following actions:
MOE has approved BGM’s request for a by-pass authorization from Feb. 11 – March 31, 2015 to allow the mine to pump untreated water into Cadwallader Creek. Under the authorization, BGM must:
IHA has determined, based on the dilution effect of the creek into Carpenter Lake, that these elements pose no known health risks at this time. IHA will continue to monitor conditions and provide an update if required.
The Bralorne Gold Mine has temporarily ceased operations. It is a small underground gold mining operation located in southwest B.C., approximately 130 kilometres from Lillooet.