Follow Us! Like Our Page!

NorZinc Receives Final Major Permits for Prairie Creek Mine

Press Release

November 25, 2019 ─ Vancouver, British Columbia ─ NorZinc Ltd. (TSX: NZC; OTCQB: NORZF) (the “Company” or “NorZinc”) is very pleased to report that on November 22, 2019, Parks Canada (“Parks”) issued the Water Licence and Land Use Permit for its portion of the all season access road to the Prairie Creek Mine, NWT, Canada.

Permitting Process Complete

Combined with NorZinc’s existing mine operating permits, and the road permits issued by the Mackenzie Valley Land & Water Board (”MVLWB”) on November 13, 2019, NorZinc now has all major permits necessary for construction and operation of the Prairie Creek Mine, and all season access road. The all season road will provide the mine with year round access to Canada’s national transportation network.

Construction and Schedule

As previously announced, NorZinc plans to develop the Prairie Creek Mine in two phases. Prior to major construction on site, Phase 1 will start with the construction of an initial 170km winter road to the Prairie Creek Mine site, planned for Q1 2020. Prior to commencing that winter road construction, NorZinc must obtain approval from both the MVLWB and Parks of a series of updated road Management Plans. The timing of issuance of the road permits, and the time for the review process required for the Management Plans, has made it necessary to consider alternative road construction options to retain schedule. The Company, working with the road contractor and local First Nations, has developed an alternative road construction schedule, the success of which will be dependent on the timing of approval of the Management Plans. NorZinc will be providing more details on this and other important developments in the coming weeks.

Don MacDonald, President & CEO of NorZinc Ltd. stated, “I would like to thank all those inside and outside of NorZinc who have put in so much hard work, over so many years, to make this day possible. We finally have the last major permit in place to build the Prairie Creek Mine and will be working very hard over the coming weeks to present, and obtain approval for, the management and monitoring plans for the all season road so we can advance construction and start to build.” MacDonald added, “The timely approval of the management plans will be critical for us to continue to meet our development schedule outlined over 16 months ago. It is also critical that we develop the Prairie Creek Mine in a manner that is the most environmentally sustainable and with the strongest local indigenous support.”

Financing for Road Construction in 2020

Readers are encouraged to refer to the Company’s news release dated November 14, 2019 for NorZinc’s current financing plans. NorZinc will provide further updates as the timing of review and approval of the Management Plans becomes more certain. That timing is expected to affect the financing needs over the coming quarters.

About NorZinc

NorZinc is a TSX-listed mine development Company trading under the symbol “NZC”. The Company is developing its key project, the 100%-owned high grade zinc-lead-silver Prairie Creek Mine, located in the Northwest Territories. The Company also owns projects in Newfoundland that host several zinc-lead-copper-gold-silver deposits.

For further information contact:

Don MacDonald Steve Dawson
President & CEO VP Corporate Development
(604) 688-2001 (416) 203-1418
Suite 1710 – 650 West Georgia Street, Suite 1805, 55 University Avenue,
Vancouver, BC V6B 4N9 Toronto, ON M5J 2H7
don.macdonald@norzinc.com steve.dawson@norzinc.com

Tollfree:1-866-688-2001  E-mail: invest@norzinc.com  Website: www.norzinc.com